Summary
B0301925
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
PARTIAL COMMERCIAL
BLDG D FOUND & UNDERSLAB
09/24/2003
10/28/2003
04/25/2004
09/15/2004
Locations
Contacts
JE DUNN CONSTRUCTION CO., Address:929 HOLMES  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 03/22/2004 10/29/2010
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

Fire Department- Egress doors shall be readily openable from the egress side without the use of akey or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

Fire Department- The maximum occupant load shall be posted in potential assembly areas such as the track.
Correction

Fire Department- Indicate the type of sanitizing system used on the pool.
Correction

St. Lukes - The City shall not issue any temporary or final Certificate of Occupancy for any structure in the Developerment until a Certificate of Substantial Completion for the Road Improvements has been issued by MoDOT.
Correction

St. Lukes - A Proprtionate Share of the Total Road Contribution shall be made to the City at or before the time a certificate of occupancy is issued by the City for a building constructed by, or by a building contractor on behalf of, the Developer on the Property, excluding the medical office buildings.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

1003.2.10.1 Fire Department- Where required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. Access to exits shall be marked by readily visible exit signs in cases where the exit or the path of egress travel is not immediately visible to the occupants. Exit sign placement shall be such that no point in an exit access corridor is more than 100 feet (30 480 mm) from the nearest visible exit sign.
Correction

Fire Department; New and existing buildings shall have approved address numbers, building numbers, placed in a position to be plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background.
Correction

Fire Department; The required fire-resistance rating of fire-resistance-rated construction (including walls, fire stops, shaft enclosures, partitions and floors) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings, and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance rated assemblies shall be protected by self-closing or automatic- closing doors of approved construction meeting the fire protection requirements for the assembly.
Correction

Fire Department. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. The plans and specifications shall bear a State of Missouri licensed engineers seal. This includes fire sprinkler systems, grease hood and duct suppression systems as well as other fire suppression system.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-7343.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department; Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Documents shall bear a State of Missouri architect/engineers seal..Construction documents shall include, but not be limited to, all of the following: 1. A floor plan. 2. Locations of alarm-initiating and notification appli- ances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing informa- tion for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Correction

Fire Department- 907.12 Duct smoke detectors. Duct smoke detectors shall be connected to the building’s fire alarm control panel when a fire alarm system is provided. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location. Duct smoke detectors shall not be used as a substitute for required open area detection. Exceptions: 1. The supervisory signal at a constantly attended location is not required where duct smoke detectors activate the building’s alarm notification appliances. 2. In occupancies not required to be equipped with a fire alarm system, actuation of a smoke detector shall activate a visible and an audible signal in an approved location. 3. Smoke detector trouble conditions shall activate a visible or audible signal in an approved location and shall be identified as air duct detector trouble.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

905.1 General. Standpipe systems shall be provided in new buildings and structures in accordance with this section and as required by the Code Offical. Fire hose threads used in connection with standpipe systems shall comply with NFPA 1963 or as otherwise approved and shall be compatible with fire department hose threads. The location of fire department hose connections shall be approved. In build-ings used for high-piled combustible storage, fire protection shall be in accordance with Chapter 23.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $3,179.00 $3,179.00 Paid 10/28/2003
24 BLDG Plan Check Fees $72.95 $72.95 Paid 10/28/2003
25 Plumbing Permit Fees $15.00 $15.00 Paid 10/28/2003
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Foundation Inspection - Commercial Partial 03/23/2004
Correction
Partial Correction
03/23/2004
BRICK LEDGE BEAM CORRECT STIRRUP IMPINGING ON WATER STOP NEAR (7.5). SOME STIRRUPS NOT PERPENDICULAR TO LONGITUDINAL BARS. OK TO POUR WHEN READY & SEA AUTHORIZES. DETAIL 9 SHT S4.3 FRM (2.8) TO (8)
Piers/Caissons Inspection - Commercial Partial 03/29/2004
Correction
Partial Correction
03/29/2004
INTERIOR PIERS B/3; B/4; B/2; SUBJECT TO SEA APPROVAL OK TO POUR WHEN READY
Piers/Caissons Inspection - Commercial Partial 03/30/2004
Correction
Partial Correction
03/30/2004
INTERIOR PIERS B/3; B/4; B/2; B/1; C/1; C/2; C/3; C/4; D/1; D/2; SUBJECT TO SEA APPROVAL OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 04/01/2004
Correction
Partial Correction
04/01/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS ALONG (B) FRM (8) TO (6.1); ALONG (8) FRM (B) TO (B.5); ALONG (7) FRM (B) TO (B.5); OK TO POUR WHEN READY ENTRY VEST @ NE CORNER +
Piers/Caissons Inspection - Commercial Passed 04/01/2004
Correction
Resolved
04/01/2004
INTERIOR PIERS B/3; B/4; B/2; B/1; C/1; C/2; C/3; C/4; D/1; D/2; D/3; D/4; FOUR P4`S @ STAIRWELL & ELEVATOR SHAFT SUBJECT TO SEA APPROVAL OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 04/06/2004
Correction
Partial Correction
04/06/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS ALONG (B) FRM (8) TO (6.1); ALONG (8) FRM (B) TO (B.5); ALONG (7) FRM (B) TO (B.5); ON (B) W TO (5), S TO B.3; OK TO POUR WHEN READY ENTRY VEST @ NE CORNER +
Footing Inspection - Commercial Partial 04/07/2004
Correction
Resolved
04/07/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS ALONG (B) FRM (8) TO (6.1); ALONG (8) FRM (B) TO (B.5); ALONG (7) FRM (B) TO (B.5); ON (B) W TO (5), S TO B.3; ENTRY VEST @ NE CORNER +
Correction
Partial Correction
04/07/2004
GRADE BEAM & INTEGRAL BASE SLAB OK TO POUR WHEN READY STAIRWELL & ELEVATOR SHAFT
Foundation Inspection - Commercial Partial 04/08/2004
Correction
Resolved
04/08/2004
BRICK LEDGE BEAM DETAIL 9 SHT S4.3 FRM (2.8) TO (8)
Correction
Partial Correction
04/08/2004
ELEVATOR PIT WALLS SUBSTANTIALLY COMPLETED OK TO POUR WHEN READY RE-STEEL PLACEMENT
Footing Inspection - Commercial Partial 04/13/2004
Correction
Partial Correction
04/13/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS ALONG (B) FRM (8) TO (6.1); ALONG (8) FRM (B) TO (B.5); ALONG (7) FRM (B) TO (B.5); ON (B) W TO (5), S TO B.3; ALONG (B) FRM (4.5) W TO (2.5); ALONG (4) & (3) FRM (B) S TO (B.4); OK TO POUR WHEN READY ENTRY VEST @ NE CORNER +
Correction
Resolved
04/13/2004
GRADE BEAM & INTEGRAL BASE SLAB ELEVATOR SHAFT
Footing Inspection - Commercial Partial 04/14/2004
Correction
Partial Correction
04/14/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS (B) FRM (8) TO (6.1); (8) FRM (B) TO (B.5); (7) FRM (B) TO (B.5); ON (B) W TO (5), S TO B.3; (B) FRM (4.5) W TO (2.5); (4) & (3) FRM (B) S TO (B.4); ALONG (1) FRM (A.6) TO (D); ALONG (2) FRM (B) TO (B.3) ALONG (B) FRM (2.5) TO (1); OK TO POUR WHEN READY ENTRY VEST @ NE CORNER +
Correction
Partial Correction
04/14/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D ALONG (C) & (D) FRM (1) TO (1.5); N WALL OF STAIRWELL; OK TO POUR WHEN READY ENSURE REBAR COVERAGE
Footing Inspection - Commercial Partial 04/15/2004
Correction
Partial Correction
04/15/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D ALONG (C) & (D) FRM (1) TO (1.5); N WALL OF STAIRWELL; ALL W OF (3.3); OK TO POUR WHEN READY ENSURE REBAR COVERAGE
Footing Inspection - Commercial Partial 04/16/2004
Correction
Partial Correction
04/16/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D ALONG (C) & (D) FRM (1) TO (1.5); N WALL OF STAIRWELL; ALL W OF (3.3); E OF (3.3) & W OF 4.4 & S OF B.3; OK TO POUR WHEN READY ENSURE REBAR COVERAGE
Water Service Inspection Partial 04/19/2004
Correction
Partial Correction
04/19/2004
DOMESTIC & FIRE FEEDERS EXCEPT 45d BENDS + ~ 14` NORTH -- VISUAL OK. FIRE LINE HELD 98 PSI PRESSURE TEST STEADY FOR > 60 MIN. DOMESTIC LINE LOST PRESSURE. FROM METER PIT TO TUNNEL ENTRY @STA 1+76.82
Footing Inspection - Commercial Passed 04/19/2004
Correction
Resolved
04/19/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS (B) FRM (8) TO (6.1); (8) FRM (B) TO (B.5); (7) FRM (B) TO (B.5); ON (B) W TO (5), S TO B.3; (B) FRM (4.5) W TO (2.5); (4) & (3) FRM (B) S TO (B.4); ALONG (1) FRM (A.6) TO (D); ALONG (2) FRM (B) TO (B.3) ALONG (B) FRM (2.5) TO (1); ENTRY VEST @ NE CORNER +
Correction
Resolved
04/19/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS, CONT'D ALONG (C) & (D) FRM (1) TO (1.5); N WALL OF STAIRWELL; ALL W OF (3.3); E OF (3.3) & W OF 4.4 & S OF B.3; ALL REMAINING E OF (4.4) OK TO POUR WHEN READY ENSURE REBAR COVERAGE
Underslab Plumbing Inspection - Commercial Partial 04/21/2004
Correction
Partial Correction
04/21/2004
UNDER-SLAB DWV PIPING ALONG (A.7) FRM (1) TO (4.5); ALONG (2.8) FRM TUNNEL TO (B.2); VISUAL OK; COVER AT RISK PRESSURE TEST TO FOLLOW
Underslab Plumbing Inspection - Commercial Partial 04/22/2004
Correction
Partial Correction
04/22/2004
UNDER-SLAB DWV PIPING ALONG (A.7) FRM (1) TO (4.5); ALONG (2.8) FRM TUNNEL TO (B.2); REMAINDER WEST OF (5); VISUAL & PRESSURE TEST OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Partial 04/23/2004
Correction
Partial Correction
04/23/2004
UNDER-SLAB STORM DRAIN EXCEPT S30' TO BLDG ENTRY VISUAL OK
Underslab Plumbing Inspection - Commercial Partial 04/26/2004
Correction
Partial Correction
04/26/2004
UNDER-SLAB STORM DRAIN VISUAL OK S 30' TO NEAR BLDG ENTRY NOW COMPLETED; + 20' TO W
Underslab Plumbing Inspection - Commercial Partial 04/27/2004
Correction
Partial Correction
04/27/2004
UNDER-SLAB STORM DRAIN TEST OK S 30' TO NEAR BLDG ENTRY NOW COMPLETED; + 20' TO W
Underslab Plumbing Inspection - Commercial Partial 04/30/2004
Correction
Partial Correction
04/30/2004
UNDER-SLAB DWV PIPING ALONG (A.7) FRM (1) TO (4.5); ALONG (2.8) FRM TUNNEL TO (B.2); REMAINDER WEST OF (5); ALONG (C.8) FRM (4.8) TO (8); VISUAL & PRESSURE TEST OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Partial 06/01/2004
Correction
Partial Correction
06/01/2004
UNDER-SLAB DWV PIPING PRESSURE TEST OK: ALONG (A.7) FRM (1) TO (4.5); ALONG (2.8) FRM TUNNEL TO (B.2); REMAINDER WEST OF (5); ALONG (C.8) FRM (4.8) TO (8) VISUAL INSPECTION OK (7) TO (8) x TUNNEL TO D;
Underslab Plumbing Inspection - Commercial Partial 06/02/2004
Correction
Resolved
06/02/2004
UNDER-SLAB STORM DRAIN
Correction
Partial Correction
06/02/2004
UNDER-SLAB DWV PIPING PRESSURE TEST OK: (7) TO (8) x TUNNEL TO (D); TUNNEL TO (B.5) E OF (6); ALONG (A.7) FRM (1) TO (4.5); ALONG (2.8) FRM TUNNEL TO (B.2); REMAINDER WEST OF (5); ALONG (C.8) FRM (4.8) TO (8) VISUAL INSPECTION OK
Underslab Plumbing Inspection - Commercial Passed 06/03/2004
Correction
Resolved
06/03/2004
UNDER-SLAB DWV PIPING (6) TO (7) x (B.7) TO (D); (7) TO (8) x TUNNEL TO (D); TUNNEL TO (B.5) E OF (6); ALONG (A.7) FRM (1) TO (4.5); ALONG (2.8) FRM TUNNEL TO (B.2); REMAINDER WEST OF (5); ALONG (C.8) FRM (4.8) TO (8) VISUAL INSPECTION OK PRESSURE TEST OK
Underslab Electrical Inspection - Commercial Partial 06/15/2004
Correction
Partial Correction
06/15/2004
CONDUIT & BOXES UNDER 1ST FLR S.O.G. (4) TO (5.2) x TUNNEL TO (D); MATERIAL & WORKMANSHIP OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Passed 09/02/2004
Correction
Resolved
09/02/2004
UNDER-SLAB PLUMBING @ SUNKEN POOL INSPECTED PER FERNO POOLS DRWG# 52-71076 NOT ON PERMIT DRAWINGS WORKMANSHIP & MATERIAL OK
Footing Inspection - Commercial Passed 09/09/2004
Correction
Resolved
09/09/2004
POOL BOTTOM SLAB POUR PREP WORKMANSHIP OK NOT SHOWN ON PERMIT DRWGS EPOXY-COATED RE-BAR @ 12"
Pool Steel/Bonding - Commercial Partial 09/14/2004
Correction
Partial Correction
09/14/2004
UNDER-SLAB BONDING CONDUCTOR MATERIAL CONDITION & WORKMANSIP OK STUBBED-UP BOTH ENDS NOT ON PERMIT DRAWINGS
Foundation Inspection - Commercial Passed 09/14/2004
Correction
Resolved
09/14/2004
THERAPY POOL WALLS WATER STOP @ KEYWAY PER ADDENDUM 4.0 #4 COATED RE-BAR @ 12" EW
Correction
Resolved
09/14/2004
ELEVATOR PIT WALLS
Final Inspection - Commercial Passed 09/14/2004
Correction
Resolved
09/14/2004
CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home