Summary
B0301924
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
PARTIAL COMMERCIAL
BLDG C FOUND & UNDERSLAB
09/24/2003
10/28/2003
04/25/2004
01/06/2005
Locations
Contacts
JE DUNN CONSTRUCTION CO., Address:929 HOLMES  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 03/22/2004 10/29/2010
Correction

St. Lukes - The City shall not issue any temporary or final Certificate of Occupancy for any structure in the Developerment until a Certificate of Substantial Completion for the Road Improvements has been issued by MoDOT.
Correction

St. Lukes - A Proprtionate Share of the Total Road Contribution shall be made to the City at or before the time a certificate of occupancy is issued by the City for a building constructed by, or by a building contractor on behalf of, the Developer on the Property, excluding the medical office buildings.
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $2,462.00 $2,462.00 Paid 10/28/2003
24 BLDG Plan Check Fees $61.00 $61.00 Paid 10/28/2003
25 Plumbing Permit Fees $15.00 $15.00 Paid 10/28/2003
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 11/07/2003
Correction
Partial Correction
11/07/2003
COLUMN FOOTINGS OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3; D.5/2; F/3
Foundation Inspection - Commercial Partial 11/11/2003
Correction
Partial Correction
11/11/2003
TUNNEL-LEVEL COLUMNS A.4/1.5; A.7/2 OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 11/12/2003
Correction
Partial Correction
11/12/2003
TUNNEL-LEVEL COLUMN B/1 OK TO POUR WHEN READY
Correction
Resolved
11/12/2003
TUNNEL-LEVEL COLUMNS A.4/1.5; A.7/2
Footing Inspection - Commercial Partial 11/21/2003
Correction
Partial Correction
11/21/2003
COLUMN FOOTINGS OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3; D.5/2; F/3; F/4; F.6/4;
Footing Inspection - Commercial Partial 12/31/2003
Correction
Partial Correction
12/31/2003
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3;
Foundation Inspection - Commercial Partial 01/08/2004
Correction
Resolved
01/08/2004
TUNNEL-LEVEL COLUMN
Correction
Partial Correction
01/08/2004
TUNNEL-LEVEL COLUMNS G/5; G/6; G/7 OK IF SEA APPROVES VERTICAL BAR LAP; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; H/4;
Foundation Inspection - Commercial Partial 02/18/2004
Correction
Partial Correction
02/18/2004
TUNNEL-LEVEL COLUMNS G/5; G/6; G/7; F.8/9; G.2/9; JJ/44; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; H/4;
Footing Inspection - Commercial Partial 02/27/2004
Correction
Partial Correction
02/27/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3;
Foundation Inspection - Commercial Partial 03/08/2004
Correction
Partial Correction
03/08/2004
TUNNEL-LEVEL COLUMNS G/5; G/6; G/7; F.8/9; G.2/9; JJ/44; J/5; J/6; J/7; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; H/4;
Footing Inspection - Commercial Partial 03/08/2004
Correction
Partial Correction
03/08/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3;
Foundation Inspection - Commercial Partial 03/09/2004
Correction
Partial Correction
03/09/2004
TUNNEL-LEVEL COLUMNS G/5; G/6; G/7; F.8/9; G.2/9; JJ/44; J/5; J/6; J/7; J/4; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; H/4;
Footing Inspection - Commercial Partial 03/17/2004
Correction
Partial Correction
03/17/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; DOWEL PLACEMENT IN PROGRESS INSP BY SEA OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3;
Footing Inspection - Commercial Partial 03/18/2004
Correction
Partial Correction
03/18/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; NOT READY: E.6/7.05; F/8; F.5/8.4; F/8.6; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3;
Correction
Corrective Action Required
03/18/2004
GRADE BEAM @ N EXTERIOR RADIUS WALL NOT READY
Footing Inspection - Commercial Partial 03/19/2004
Correction
Partial Correction
03/19/2004
COLUMN FOOTINGS E.8, DD5.5, CB5.5, 6B APPROVED OK TO COVER
Footing Inspection - Commercial Partial 03/19/2004
Correction
Partial Correction
03/19/2004
COLUMN FOOTINGS E.6/7.05, F8, F/8.6, F.5/8.4, E.6/8.2 OK TO COVER
Correction
Resolved
03/19/2004
GRADE BEAM @ N EXTERIOR RADIUS WALL
Underslab Plumbing Inspection - Commercial Partial 03/23/2004
Correction
Partial Correction
03/23/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL PRESSURE TESTED; C/3.7 S TO F.2/3.7 SW THRU TUNNEL > PRESSURE TEST TO FOLLOW OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Partial 03/24/2004
Correction
Partial Correction
03/24/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL; C/3.7 S TO F.2/3.7 SW THRU TUNNEL -- PRESSURE TESTED OK TO COVER WHEN READY
Correction
Partial Correction
03/24/2004
C.I. DWV PIPING 4" SAN + BRANCHES ALONG (3.9) FRM TUNNEL N TO A.8/4; OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Passed 03/25/2004
Correction
Resolved
03/25/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL; C/3.7 S TO F.2/3.7 SW THRU TUNNEL
Correction
Resolved
03/25/2004
C.I. DWV PIPING 4" SAN + BRANCHES ALONG (3.9) FRM TUNNEL N TO A.8/4; THRU TUNNEL @ G.3/4.4, E ALONG G.3 + BRANCHES TO 8.9 OK TO COVER WHEN READY
Footing Inspection - Commercial Partial 03/25/2004
Correction
Resolved
03/25/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; NOT READY: E.6/7.05; F/8; F.5/8.4; F/8.6; A.4/1.5; A.7/2; B/1; D/3;
Correction
Partial Correction
03/25/2004
GRADE BEAM @ E EXTERIOR WALL FRM JJ TO DD.5; BB.5 TO AA; ALONG C/L 44 OK TO POUR WHEN READY
Correction
Resolved
03/25/2004
COLUMN FOOTINGS E.8, DD5.5, CB5.5, 6B
Correction
Resolved
03/25/2004
COLUMN FOOTINGS E.6/7.05, F8, F/8.6, F.5/8.4, E.6/8.2
Footing Inspection - Commercial Passed 03/26/2004
Correction
Resolved
03/26/2004
GRADE BEAM @ E EXTERIOR WALL FRM JJ TO DD.5; BB.5 TO AA; DD.5 TO BB.5 + ENTRY FOUNDATION PAD ALONG C/L 44 OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 03/31/2004
Correction
Partial Correction
03/31/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; E.6/7.05; F/8; F.5/8.4; F/8.6; G/2; G/3; F/2; A.4/1.5; A.7/2; B/1; D/3;
Correction
Resolved
03/31/2004
GRADE BEAM @ E EXTERIOR WALL FRM JJ TO DD.5; BB.5 TO AA; DD.5 TO BB.5 + ENTRY FOUNDATION PAD ALONG C/L 44
Footing Inspection - Commercial Partial 04/02/2004
Correction
Partial Correction
04/02/2004
GRADE BEAM @ W & S WALLS FRM 10` S OF E.2/5.2 SW , THEN S TO G.5 ALONG (1); INCL INTEGRAL COL FOOT'GS OK TO POUR WHEN READY
Correction
Partial Correction
04/02/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; E.6/7.05; F/8; F.5/8.4; F/8.6; G/2; G/3; F/2; D.5/1; A.4/1.5; A.7/2; B/1; D/3;
Underslab Plumbing Inspection - Commercial Partial 04/05/2004
Correction
Partial Correction
04/05/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL; C/3.7 S TO F.2/3.7 SW THRU TUNNEL; I/S GRD BM FRM B:E.2/5.2 SE TO 45d NEAR C:F/1; OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Partial 04/06/2004
Correction
Partial Correction
04/06/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL; C/3.7 S TO F.2/3.7 SW THRU TUNNEL; I/S GRD BM FRM B:E.2/5.2 SE TO 45d NEAR C:F/1 + S TO G.3/3.8 + SW 20` PRESS TEST TO FOLLOW; OK TO COVER WHEN READY
Footing Inspection - Commercial Partial 04/06/2004
Correction
Partial Correction
04/06/2004
GRADE BEAM @ W & S WALLS FRM 10` S OF E.2/5.2 SW , THEN S TO G.5 ALONG (1); INCL INTEGRAL COL FOOT'GS
Correction
Partial Correction
04/06/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; E.6/7.05; F/8; F.5/8.4; F/8.6; G/2; G/3; F/2; D.5/1; J.8/1; A.4/1.5; A.7/2; B/1; D/3;
Footing Inspection - Commercial Partial 04/07/2004
Correction
Partial Correction
04/07/2004
GRADE BEAM @ W & S WALLS FRM 10` S OF E.2/5.2 SW , THEN S TO G.5 ALONG (1); ALONG (K) FRM (2.5) TO (7.5); INCL INTEGRAL COL FOOT'GS OK TO POUR WHEN READY
Underslab Plumbing Inspection - Commercial Partial 04/07/2004
Correction
Partial Correction
04/07/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL; C/3.7 S TO F.2/3.7 SW THRU TUNNEL; I/S GRD BM FRM B:E.2/5.2 SE TO 45d NEAR C:F/1 + S TO G.3/3.8 + SW 20`
Correction
Resolved
04/07/2004
C.I. DWV PIPING 4" SAN + BRANCHES ALONG (3.9) FRM TUNNEL N TO A.8/4; THRU TUNNEL @ G.3/4.4, E ALONG G.3 + BRANCHES TO 8.9; (F) TO (H) x TUNNEL TO 15` WEST -- PRESSURE TEST TO FOLLOW; OK TO COVER WHEN READY
Underslab Plumbing Inspection - Commercial Passed 04/08/2004
Correction
Resolved
04/08/2004
C.I. STORM DRAIN FRM F/8.6 W TO F/5 THE SW THRU TUNNEL; C/3.7 S TO F.2/3.7 SW THRU TUNNEL; I/S GRD BM FRM B:E.2/5.2 SE TO 45d NEAR C:F/1 + S TO G.3/3.8 + SW 20`
Correction
Resolved
04/08/2004
C.I. DWV PIPING 4" SAN + BRANCHES ALONG (3.9) FRM TUNNEL N TO A.8/4; THRU TUNNEL @ G.3/4.4, E ALONG G.3 + BRANCHES TO 8.9; (F) TO (H) x TUNNEL TO 15` WEST; ALL N OF (J) VISUAL + PRESSURE TEST OK OK TO COVER WHEN READY
Footing Inspection - Commercial Not Ready 04/08/2004
Correction
Resolved
04/08/2004
GRADE BEAM @ W & S WALLS FRM 10` S OF E.2/5.2 SW , THEN S TO G.5 ALONG (1); ALONG (K) FRM (2.5) TO (7.5); INCL INTEGRAL COL FOOT'GS
Correction
Corrective Action Required
04/08/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; E.6/7.05; F/8; F.5/8.4; F/8.6; G/2; G/3; F/2; D.5/1; J.8/1; {H-J/2; H-J/3 NOT READY} A.4/1.5; A.7/2; B/1; D/3;
Footing Inspection - Commercial Partial 04/09/2004
Correction
Partial Correction
04/09/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; E.6/7.05; F/8; F.5/8.4; F/8.6; G/2; G/3; F/2; D.5/1; J.8/1; H-J/2; H-J/3 DOWEL PLACEMENT IN PROGRESS; OK TO POUR WHEN READY A.4/1.5; A.7/2; B/1; D/3;
Underslab Electrical Inspection - Commercial Partial 04/14/2004
Correction
Partial Correction
04/14/2004
CONDUIT @ RMS C192 & C194 + EAST INTO TUNNEL OK TO COVER WHEN READY
Footing Inspection - Commercial Partial 04/16/2004
Correction
Resolved
04/16/2004
GRADE BEAM @ W & S WALLS FRM 10` S OF E.2/5.2 SW , THEN S TO G.5 ALONG (1); ALONG (K) FRM (2.5) TO (7.5); ALONG (1) FRM (G.5) S TO (K), THEN E TO (2.5); OK TO POUR WHEN READY INCL INTEGRAL COL FOOT'GS ENSURE 3" REBAR COVERAGE
Underslab Plumbing Inspection - Commercial Not Ready 06/08/2004
Correction
Resolved
06/08/2004
C.I. DWV PIPING 4" SAN + BRANCHES ALONG (3.9) FRM TUNNEL N TO A.8/4; THRU TUNNEL @ G.3/4.4, E ALONG G.3 + BRANCHES TO 8.9; (F) TO (H) x TUNNEL TO 15` WEST; ALL N OF (J) VISUAL + PRESSURE TEST OK
Correction
Corrective Action Required
06/08/2004
C.I. DWV PIPING S OF (H) NOT FOUND ON PERMIT DRWGS NOT READY FOR INSPECTION
Underslab Plumbing Inspection - Commercial Partial 06/09/2004
Correction
Resolved
06/09/2004
C.I. STORM DRAIN C/3.7 S TO F.2/3.7 SW THRU TUNNEL; I/S GRD BM FRM B:E.2/5.2 SE TO 45d NEAR C:F/1 + S TO G.3/3.8 + SW 20`; 15" C.I. DS ALONG (3.8) FROM (H) TO (K) VISUAL OK - PRESS TEST WAIVED; FRM F/8.6 W TO F/5 THEN SW THRU TUNNEL;
Correction
Corrective Action Required
06/09/2004
C.I. DWV PIPING S OF (H) TO BE COMPLETED &APPROVED
Underslab Plumbing Inspection - Commercial Passed 06/10/2004
Correction
Resolved
06/10/2004
C.I. DWV PIPING S OF (H) VISUAL OK; PRESSURE TEST WAIVED DUE TO CONFIGURATION ALONG (3.9) FROM (H) TO M.H. S OF (K)
Footing Inspection - Commercial Partial 06/22/2004
Correction
Resolved
06/22/2004
CANOPY COLUMN FOOTINGS CC/22; DD/22; CC/11; DD/11 PREP IN PROGRESS OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 06/23/2004
Correction
Resolved
06/23/2004
CANOPY COLUMN FOOTINGS CC/22; DD/22; CC/11; DD/11 PREP IN PROGRESS
Correction
Resolved
06/23/2004
FOOTING "BUMP-OUT" @ AA/44 PER RFI #105 DRWG XS-128 TRIM S BANK FOR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Passed 06/24/2004
Correction
Resolved
06/24/2004
COLUMN FOOTINGS D.5/2; F/3; F/4; F.6/4; G/6; G/7; J/5; J/6; J/7; J/4; A.8/4; D/4; A.5/5; D/5; F/5; A.9/3; A/5.5; E/6; F/6; E.6/7.05; F/8; F.5/8.4; F/8.6; G/2; G/3; F/2; D.5/1; J.8/1; H-J/2; H-J/3 DOWEL PLACEMENT IN PROGRESS; A.4/1.5; A.7/2; B/1; D/3;
Correction
Resolved
06/24/2004
FOOTING "BUMP-OUT" @ AA/44 TRIM S BANK FOR COVERAGE PER RFI #105 DRWG XS-128
Correction
Resolved
06/24/2004
FOOTING MODIFICATION FOR DOOR @ K/5 PER XS- 201
Underground Electrical Inspection - Commercial Partial 09/28/2004
Correction
Partial Correction
09/28/2004
LIGHTNING PROTECTION GROUNDING 3 GROUND RODS & CABLE N&W OF FRONT ENTRANCE
Underground Electrical Inspection - Commercial Not Ready 09/30/2004
Correction
Partial Correction
09/30/2004
LIGHTNING PROTECTION GROUNDING E&S OF FRONT ENTRANCE WORK IN PROGRESS - NOT READY OK TO COVER WHEN READY N&W OF FRONT ENTRANCE OK
Underground Electrical Inspection - Commercial Partial 10/05/2004
Correction
Partial Correction
10/05/2004
LIGHTNING PROTECTION GROUNDING E&S OF FRONT ENTRANCE WORK IN PROGRESS OK OK TO COVER WHEN READY N&W OF FRONT ENTRANCE OK
Underslab Plumbing Inspection - Commercial Passed 10/13/2004
Correction
Resolved
10/13/2004
C.I. STORM DRAIN
Correction
Resolved
10/13/2004
C.I. DWV PIPING
Correction
Resolved
10/13/2004
C.I. DWV PIPING S OF (H)
Footing Inspection - Commercial Passed 10/13/2004
Correction
Resolved
10/13/2004
COLUMN FOOTINGS
Correction
Resolved
10/13/2004
GRADE BEAM @ N EXTERIOR RADIUS WALL
Correction
Resolved
10/13/2004
COLUMN FOOTINGS
Correction
Resolved
10/13/2004
COLUMN FOOTINGS
Correction
Resolved
10/13/2004
GRADE BEAM @ E EXTERIOR WALL
Correction
Resolved
10/13/2004
GRADE BEAM @ W & S WALLS
Correction
Resolved
10/13/2004
CANOPY COLUMN FOOTINGS
Correction
Resolved
10/13/2004
FOOTING "BUMP-OUT" @ AA/44
Correction
Resolved
10/13/2004
FOOTING MODIFICATION FOR DOOR @ K/5
Underground Electrical Inspection - Commercial Partial 10/21/2004
Correction
Partial Correction
10/21/2004
LIGHTNING PROTECTION GROUNDING E&S OF FRONT ENTRANCE; GROUND ROD @ JJ/44 LAID HORIZONTAL IN TRENCH OVER ROCK + CONDUCTOR TRENCHED 20' N OUTSIDE WALL OK TO COVER WHEN READY N&W OF FRONT ENTRANCE;
Underground Electrical Inspection - Commercial Partial 10/22/2004
Correction
Partial Correction
10/22/2004
LIGHTNING PROTECTION GROUNDING E&S OF FRONT ENTRANCE; GROUND ROD @ JJ/44 LAID HORIZONTAL IN TRENCH OVER ROCK + CONDUCTOR TRENCHED 20' N OUTSIDE WALL; OUTSIDE WALL FROM K/1 TO K/7; OK TO COVER WHEN READY N&W OF FRONT ENTRANCE;
Footing Inspection - Commercial Passed 11/19/2004
Correction
Resolved
11/19/2004
GRADE BEAM @ TRASH ENCLOSURE NOT FOUND ON PERMIT DRWGS MATERIAL & WORKMANSHIP OK
Underground Electrical Inspection - Commercial Passed 12/22/2004
Correction
Resolved
12/22/2004
LIGHTNING PROTECTION GROUNDING E&S OF FRONT ENTRANCE; GROUND ROD @ JJ/44 LAID HORIZONTAL IN TRENCH OVER ROCK + CONDUCTOR TRENCHED 20' N OUTSIDE WALL; OUTSIDE WALL FROM K/1 TO K/7; O/S WALL @ (1) FROM (F) TO (K) OK TO COVER WHEN READY N&W OF FRONT ENTRANCE;
Final Inspection - Commercial Passed 12/22/2004
Correction
Resolved
12/22/2004
CLOSE PERMIT
Foundation Inspection - Commercial Passed 12/22/2004
Correction
Resolved
12/22/2004
TUNNEL-LEVEL COLUMNS
Underslab Electrical Inspection - Commercial Passed 12/22/2004
Correction
Resolved
12/22/2004
CONDUIT @ RMS C192 & C194
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home