Permit Application Status

B0301922


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
B0301922
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
PARTIAL COMMERCIAL
BLDG A FOUND & UNDERSLAB
09/24/2003
10/28/2003
04/25/2004
11/05/2004
Locations
Contacts
JE DUNN CONSTRUCTION CO., Address:929 HOLMES  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 03/22/2004 10/29/2010
Correction

CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
Correction

St. Lukes - The City shall not issue any temporary or final Certificate of Occupancy for any structure in the Developerment until a Certificate of Substantial Completion for the Road Improvements has been issued by MoDOT.
Correction

St. Lukes - A Proprtionate Share of the Total Road Contribution shall be made to the City at or before the time a certificate of occupancy is issued by the City for a building constructed by, or by a building contractor on behalf of, the Developer on the Property, excluding the medical office buildings.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $3,119.00 $3,119.00 Paid 10/28/2003
24 BLDG Plan Check Fees $71.95 $71.95 Paid 10/28/2003
25 Plumbing Permit Fees $15.00 $15.00 Paid 10/28/2003
Inspection Overtime $30.00 $30.00 Paid 12/01/2003
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 10/29/2003
Correction
Partial Correction
10/29/2003
None ALL OF NORTH 7 LINE A-D FOOTING PER DET 3 S1.3 INCLUSIVE OF F9/F10 FOOTINGS PER SCH 2 S 5.0 RETURNING SOUTH 16 FEET TO A 6.5 AND D6.5 APPROVED A BLDG 7 LINE NORTH FOOTING
Footing Inspection - Commercial Partial 10/30/2003
Correction
Partial Correction
10/30/2003
None EAST FOOTING A LINE FROM 6.5 SOUTH TO 4.5 PER DET 3 S1.3 INCLUSIVE OF 2 F11 COL FOOTINGS PER 2 S5.0 APPROVED BLDG A EAST FOOTING
Footing Inspection - Commercial Partial 10/31/2003
Correction
Resolved
10/31/2003
None ALL OF NORTH 7 LINE A-D FOOTING PER DET 3 S1.3 INCLUSIVE OF F9/F10 FOOTINGS PER SCH 2 S 5.0 RETURNING SOUTH 16 FEET TO A 6.5 AND D6.5 A BLDG 7 LINE NORTH FOOTING
Correction
Resolved
10/31/2003
None EAST FOOTING A LINE FROM 6.5 SOUTH TO 4.5 PER DET 3 S1.3 INCLUSIVE OF 2 F11 COL FOOTINGS PER 2 S5.0 BLDG A EAST FOOTING
Correction
Partial Correction
10/31/2003
INTERIOR COLUMN FOOTINGS OK TO POUR WHEN READY B/6 COMPLETE C/6 IN PROGRESS
Correction
Partial Correction
10/31/2003
EXTERIOR WALL FOOTING PER DET 3 S1.3 INCLUSIVE OF 2 F11 COL FOOTINGS PER 2 S5.0 (A) FRM 4.33 S TO 2.33
Underground Electrical Inspection - Commercial Partial 10/31/2003
Correction
Partial Correction
10/31/2003
PARKING LOT LIGHTING BURIED CONDUIT ENSURE TRENCH DEPTH THROUGHOUT SITE COMPLIES WITH MINIMUM COVER REQUIREMENTS IN NEC 300-5; ALSO THAT CARE IS TAKEN IN BACKFILLING PER 300-5. MATERIALS & WORKMANSHIP OBSERVED TO DATE OK
Correction
Resolved
10/31/2003
SECONDARY SERVICE FEEDER CONDUIT ADVISE CAUTION IN SELECTION OF BACKFILL MATERIAL TO ENSURE CONSOLIDATION AROUND CONDUITS N & S TRENCH DUCT BANKS OK TO COVER WHEN READY
Footing Inspection - Commercial Partial 11/03/2003
Correction
Partial Correction
11/03/2003
EXTERIOR WALL GRADE BEAM THEN W ON 1 TO A.7 OK TO POUR WHEN READY W/ INTEGRAL COL FOOTINGS E WALL COMPLETE S TO A/1
Correction
Partial Correction
11/03/2003
INTERIOR COLUMN FOOTINGS B/6; C/6
Correction
Resolved
11/03/2003
EXTERIOR WALL FOOTING OF 2 F11 COL FOOTINGS PER 2 S5.0 (A) FRM 4.33 S TO 2.33 PER DET 3 S1.3 INCLUSIVE
Footing Inspection - Commercial Partial 11/06/2003
Correction
Partial Correction
11/06/2003
EXTERIOR WALL GRADE BEAM (D) FROM (1) N TO (1.7) OK TO POUR WHEN READY W/ INTEGRAL COL FOOTINGS (7); (A); (1) COMPLETE
Underground Electrical Inspection - Commercial Failed 11/07/2003
Correction
Partial Correction
11/07/2003
LIGHT POLE BASES GROUND ROD: 1) NOT 3/4" DIAMETER 2) NOT DRIVEN FULL DEPTH 2` MIN FROM POLE BASE SHOWN ON DRWGS E1 & E2 POLE #46
Correction
Resolved
11/07/2003
PARKING LOT LIGHTING BURIED CONDUIT
Footing Inspection - Commercial Partial 11/10/2003
Correction
Partial Correction
11/10/2003
EXTERIOR WALL GRADE BEAM (D) FROM (1) N TO (1.7) W/ INTEGRAL COL FOOTINGS (7); (A); (1) COMPLETE
Correction
Partial Correction
11/10/2003
INTERIOR COLUMN FOOTINGS B/6; C/6; B/2; B/3; B/4 OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 11/11/2003
Correction
Partial Correction
11/11/2003
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS (7) FRM (D) EAST TO (B.5) OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 11/11/2003
Correction
Partial Correction
11/11/2003
EXTERIOR WALL GRADE BEAM (D) FROM (1) N TO (1.7); COL FTGS D/2; D/4 W/ INTEGRAL COL FOOTINGS (7); (A); (1) COMPLETE
Correction
Resolved
11/11/2003
INTERIOR COLUMN FOOTINGS B/6; C/6; B/2; B/3; B/4
Underground Plumbing Inspection - Commercial Partial 11/11/2003
Correction
Partial Correction
11/11/2003
U.G. STORM DRAIN PIPING PRESSURE TEST OK FROM D/1 10' N + 8" E OK TO COVER WHEN READY
Footing Inspection - Commercial Partial 11/12/2003
Correction
Partial Correction
11/12/2003
EXTERIOR WALL GRADE BEAM INTERIOR COLUMN FOOTINGS C/2; C/3 W/ INTEGRAL COL FOOTINGS ON D FRM (1.7) N TO (3.7)
Correction
Resolved
11/12/2003
EXTERIOR WALL GRADE BEAM (D) FROM (1) N TO (1.7); COL FTGS D/2; D/4 W/ INTEGRAL COL FOOTINGS (7); (A); (1) COMPLETE
Foundation Inspection - Commercial Partial 11/13/2003
Correction
Partial Correction
11/13/2003
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS (7) FRM (D) EAST TO (B.5); ON (7) E TO (A) THEN S TO (6.6); OK TO POUR WHEN READY
Underground Electrical Inspection - Commercial Partial 11/14/2003
Correction
Partial Correction
11/14/2003
LIGHT POLE BASES GROUND CONDUCTOR CONNECTION TO GROUND ROD NOT EXPOSED FOR INSPECTION. ROD LENGTH MAY NOT BE REDUCED TO SUIT CONDITIONS. SEE NEC 250-52. ADDENDUM #2 NOTED: TOP OF ROD MUST BE 3" TO 4" ABOVE BOTTOM OF TRENCH. RE-STEEL & FORMS OK. SHOWN ON DRWGS E1 & E2 POLES #42 - 48
Underslab Plumbing Inspection - Commercial Passed 11/14/2003
Correction
Resolved
11/14/2003
UNDER-FLOOR ROOF DRAIN PIPING PER ADJ DRWG AP-2 E-W @ 1.1 N FRM D TO B LOCATION & SIZE VARIES
Underground Electrical Inspection - Commercial Request Complete 11/13/2003 11/14/2003 11/14/2003
Underground Plumbing Inspection - Commercial Partial 11/18/2003
Correction
Resolved
11/18/2003
U.G. STORM DRAIN PIPING FROM D/1 10' N + 8" E
Correction
Partial Correction
11/18/2003
U.G. STORM DRAIN PIPING PROCEEDING N TO (2.6) WEST OF (D)
Foundation Inspection - Commercial Partial 11/19/2003
Correction
Partial Correction
11/19/2003
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS ON (A) FROM 6.6 S TO 4.6 OK TO POUR WHEN READY
Correction
Partial Correction
11/19/2003
INTERIOR COLUMNS B/6; C/6 OK TO POUR WHEN READY
Underground Plumbing Inspection - Commercial Partial 11/19/2003
Correction
Partial Correction
11/19/2003
U.G. STORM DRAIN PIPING OK TO COVER WHEN READY WEST OF (D) PROCEEDING N TO (3.1)
Correction
Partial Correction
11/19/2003
U.G. SANITARY SEWER PIPING OK TO COVER WHEN READY THRU GRADE BEAM @ D/2.2 THEN NORTH TO (3)
Footing Inspection - Commercial Partial 11/19/2003
Correction
Partial Correction
11/19/2003
EXTERIOR WALL GRADE BEAM W/ INTEGRAL COL FOOTINGS ON D FRM (4.5) N TO (6.6)
Correction
Resolved
11/19/2003
INTERIOR COLUMN FOOTINGS OK TO POUR WHEN READY B/6; C/6; B/2; B/3; B/4 C/4
Footing Inspection - Commercial Partial 11/20/2003
Correction
Partial Correction
11/20/2003
EXTERIOR WALL GRADE BEAM ON D FRM 3.6 TO 4.5 W/ INTEGRAL COL FOOTINGS ON D FRM (4.5) N TO (6.6)
Correction
Partial Correction
11/20/2003
INTERIOR GRADE BEAMS OK TO POUR WHEN READY BETWEEN 4 & 5 BETWEEN D & A
Underground Plumbing Inspection - Commercial Request Complete 11/20/2003 11/20/2003 11/20/2003
Foundation Inspection - Commercial Partial 11/21/2003
Correction
Partial Correction
11/21/2003
INTERIOR COLUMNS B/6; C/6; 5/B; 5/C; 5/D OK TO POUR WHEN READY
Underground Electrical Inspection - Commercial Partial 11/21/2003
Correction
Corrective Action Required
11/21/2003
LIGHT POLE BASES NOT READY FOR INSPECTION REQUESTED FOR INSPECTION 11/21/03
Underground Plumbing Inspection - Commercial Partial 11/21/2003
Correction
Partial Correction
11/21/2003
U.G. STORM DRAIN PIPING E-W BRANCH ALONG (2.8) OK TESTED & TO COVER WHEN READY WEST OF (D) PROCEEDING N TO (3.1) +
Underground Plumbing Inspection - Commercial Request Complete 11/20/2003 11/21/2003 11/21/2003
Foundation Inspection - Commercial Partial 11/24/2003
Correction
Partial Correction
11/24/2003
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS ON (A) FRM (7) S TO (2.5) OK TO POUR WHEN READY
Correction
Partial Correction
11/24/2003
INTERIOR COLUMNS OK TO POUR WHEN READY B/6; C/6; 5/B; 5/C; 5/D; B/4; C/4; D/4
Underslab Plumbing Inspection - Commercial Partial 11/24/2003
Correction
Partial Correction
11/24/2003
UNDER-SLAB SANITARY DRAIN LINE ALONG (2.2) FROM (D) EAST TO (C.4)
Underground Plumbing Inspection - Commercial Request Complete 11/21/2003 11/24/2003 11/24/2003
Foundation Inspection - Commercial Partial 11/26/2003
Correction
Resolved
11/26/2003
INTERIOR COLUMNS B/3; C/3; D/3; B/2; C/2; D/2 OK TO POUR WHEN READY B/6; C/6; 5/B; 5/C; 5/D; B/4; C/4; D/4;
Underground Electrical Inspection - Commercial Partial 11/26/2003
Correction
Resolved
11/26/2003
LIGHT POLE BASES SHOWN ON DRWGS E1 & E2 POLES #42 - 48
Correction
Partial Correction
11/26/2003
PARKING LOT/DRIVE LIGHT POLE BASES + U.G. FEEDER CONDUIT POLE NUMBERS 2, 5, 12, 17, 19, 20, 26, 27, 29, 30 TRENCH & CONDUIT ONLY (NO BASE PREP) CONNECTING POLE #'S 14-27; 58-60 REQUEST INSPECTION BEFORE BASES ARE POURED PREP FOR BASES + CONDUIT IN TRENCH
Correction
Resolved
11/26/2003
LIGHT POLE BASES
Correction
Resolved
11/26/2003
SECONDARY SERVICE FEEDER CONDUIT
Underslab Plumbing Inspection - Commercial Partial 11/26/2003
Correction
Partial Correction
11/26/2003
UNDER-SLAB SANITARY DRAIN LINE ALL FROM (5.8) TO (7) AND (A) TO (D) ALONG (2.2) FROM (D) EAST TO (C.4) +
Footing Inspection - Commercial Partial 11/28/2003
Correction
Resolved
11/28/2003
INTERIOR COLUMN FOOTINGS B/6; C/6; B/2; B/3; B/4 C/4
Correction
Resolved
11/28/2003
EXTERIOR WALL GRADE BEAM ON D FRM 3.6 TO 4.5 W/ INTEGRAL COL FOOTINGS ON D FRM (4.5) N TO (6.6)
Correction
Resolved
11/28/2003
INTERIOR GRADE BEAMS BETWEEN 4 & 5 BETWEEN D & A
Correction
Partial Correction
11/28/2003
MEZZANINE COLUMN FOOTINGS MARK F-15 ON (A.6) @ 1.5; 2; 2.5; 3; 3.5; 4;
Underslab Plumbing Inspection - Commercial Partial 11/28/2003
Correction
Partial Correction
11/28/2003
UNDER-SLAB SANITARY DRAIN LINE ALL FROM (5.8) TO (7) AND (A) TO (D) + FROM (5) TO (6) AND (A) TO (D) ALONG (2.2) FROM (D) EAST TO (C.4) +
Underslab Plumbing Inspection - Commercial Partial 12/01/2003
Correction
Resolved
12/01/2003
DOMESTIC & FIRE WATER LINE ENTRIES TO BLDG UNDER W WALL GRADE BEAM TO ABOVE FLOOR INSIDE PRESSURE TEST OF TWO LINES HELD STEADY @ > 100 PSI FOR 15 MINUTES 6" C.I. + 8" C.I. FROM 5' O/S W WALL
Underground Electrical Inspection - Commercial Partial 12/02/2003
Correction
Partial Correction
12/02/2003
PARKING LOT/DRIVE LIGHT POLE BASES + U.G. FEEDER CONDUIT POLE NUMBERS 2, 3, 4, 5, 8, 9, 10, 11, 12, 17, 19, 20, 26, 27, 29, 30 OK TO POUR & COVER TRENCH & CONDUIT ONLY (NO BASE PREP) CONNECTING POLE #'S 14-27; 58-60 REQUEST INSPECTION BEFORE BASES ARE POURED CONDUIT CONNECTING 17-62-61 OK TO COVER PREP FOR BASES + CONDUIT IN TRENCH
Foundation Inspection - Commercial Partial 12/02/2003
Correction
Partial Correction
12/02/2003
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS ENSURE WATER STOP IS CLEAN & PROPERLY PLACED PRIOR TO POUR. OK TO POUR WHEN READY ON (A) FRM (7) S TO (1) ON (1) FRM (A) W TO (C)
Underslab Electrical Inspection - Commercial Partial 12/02/2003
Correction
Partial Correction
12/02/2003
UNDER-SLAB CONDUIT UNDER GRADE BEAM @ (D)/(5.3) TO 5` O/S WEST WALL OK TO COVER WHEN READY 4"SCH 40 PVC (5) TO (6) x (B) TO (D)
Foundation Inspection - Commercial Partial 12/04/2003
Correction
Partial Correction
12/04/2003
INTERIOR COLUMNS D/3; B/2; C/2; D/2; D/1 OK TO POUR WHEN READY B/6; C/6; 5/B; 5/C; 5/D; B/4; C/4; D/4; B/3; C/3;
Underslab Plumbing Inspection - Commercial Partial 12/04/2003
Correction
Partial Correction
12/04/2003
UNDER-SLAB SANITARY DRAIN LINE FROM (5.8) TO (7) AND (A) TO (D) + FROM (5) TO (6) AND (A) TO (D) + TWO BRANCHES BETWEEN (3) & (4) / (B) &(C); ALONG (2.2) FROM (D) EAST TO (C.4) +
Underground Plumbing Inspection - Commercial Partial 12/04/2003
Correction
Partial Correction
12/04/2003
U.G. STORM DRAIN PIPING E-W BRANCH ALONG (2.8) WEST OF (D) PROCEEDING N TO (3.1) +
Correction
Partial Correction
12/04/2003
U.G. SANITARY SEWER PIPING THRU GRADE BEAM @ D/2.2 THEN NORTH TO (3)
Correction
Partial Correction
12/04/2003
STORM DRAIN PIPING W OF (D) AT/NEAR MANHOLE PRESSURE TEST & VISUAL OK
Underslab Plumbing Inspection - Commercial Partial 12/05/2003
Correction
Partial Correction
12/05/2003
UNDERSLAB SANITARY LINE SANITARY LINE FROM 3.3 TO 4.5 --C.I. 2/3/4 IN BRANCH AND MAIN WEST FROM A TO B LINE FROM A LINE VISUAL AND PRESSURE TEST
Underground Plumbing Inspection - Commercial Partial 12/05/2003
Correction
Partial Correction
12/05/2003
U.G. SANITARY PIPING 20 FEET 6 IN C. I. NOTRH TO 4 LINE TURNING EAST UNDER GRADE BEAM 10 FEET PARALLEL TO 4 LINE PRESSURE TEST AND VISUAL
Underground Electrical Inspection - Commercial Partial 12/08/2003
Correction
Partial Correction
12/08/2003
PARKING LOT/DRIVE LIGHT POLE BASES + U.G. FEEDER CONDUIT PREP FOR BASES + CONDUIT IN TRENCH POLE NUMBERS 2, 3, 4, 5, 8, 9, 10, 11, 12, 17, 19, 20, 26, 27, 29, 30 TRENCH & CONDUIT ONLY (NO POLE BASE PREP) CONNECTING POLE #'S 14-27; 17/62/61; 37-40; 58-60 REQUEST INSPECTION BEFORE BASES ARE POURED
Underslab Plumbing Inspection - Commercial Partial 12/09/2003
Correction
Partial Correction
12/09/2003
UNDER-SLAB SANITARY DRAIN LINE FROM (5.8) TO (7) AND (A) TO (D) + FROM (5) TO (6) AND (A) TO (D) + TWO BRANCHES BETWEEN (3) & (4) / (B) &(C); ALONG (B.2) FROM (3) TO (4); ALONG (2.2) FROM (D) EAST TO (C.4) +
Correction
Resolved
12/09/2003
UNDERSLAB SANITARY LINE SANITARY LINE FROM 3.3 TO 4.5 --C.I. 2/3/4 IN BRANCH AND MAIN WEST FROM A TO B LINE FROM A LINE VISUAL AND PRESSURE TEST
Underslab Plumbing Inspection - Commercial Partial 12/11/2003
Correction
Partial Correction
12/11/2003
UNDER-SLAB SANITARY DRAIN LINE ALONG (2.2) FROM (D) EAST TO (C.4) + FROM (5.8) TO (7) AND (A) TO (D) + FROM (5) TO (6) AND (A) TO (D) + TWO BRANCHES BETWEEN (3) & (4) / (B) &(C); ALONG (B.2) FROM (3) TO (4); MAIN BRANCH ALONG (3.8) FRM (B) TO (D) + BRANCH DRAIN LINES;
Underslab Plumbing Inspection - Commercial Partial 12/12/2003
Correction
Partial Correction
12/12/2003
UNDER-SLAB SANITARY DRAIN LINE ALONG (2.2) FRM (D) EAST TO (C.4) + FRM (5.8) TO (7) AND (A) TO (D) + FRM (5) TO (6) AND (A) TO (D) + TWO BRCHS BETW (3) & (4) / (B) &(C); ALONG (B.2) FRM (3) TO (4); MAIN BR ALONG (3.8) FRM (B) TO (D) + BRANCH DRAIN LINES; (1) / (3) x (A) / (A.3);
Underslab Plumbing Inspection - Commercial Partial 12/15/2003
Correction
Resolved
12/15/2003
UNDER-SLAB SANITARY DRAIN LINE ALONG (2.2) FRM (D) EAST TO (C.4) + FRM (5.8) TO (7) AND (A) TO (D) + FRM (5) TO (6) AND (A) TO (D) + TWO BRCHS BETW (3) & (4) / (B) &(C); ALONG (B.2) FRM (3) TO (4); MAIN BR ALONG (3.8) FRM (B) TO (D) + BRANCH DRAIN LINES; (1) / (3) x (A) / (A.3);
Correction
Partial Correction
12/15/2003
UNDER-SLAB SANITARY DRAIN LINE FROM (2.1) TO (1.4) (2) TO (3) x (A.4) TO (B) + N-S ALONG A.8
Underslab Plumbing Inspection - Commercial Partial 12/17/2003
Correction
Partial Correction
12/17/2003
UNDER-SLAB SANITARY DRAIN LINE FROM (2.1) TO (1.4); ALL REMAINING FROM (1) TO (3) EXCEPT ALONG (C.7) BETWEEN (1) & (2) (2) TO (3) x (A.4) TO (B) + N-S ALONG A.8
Underslab Plumbing Inspection - Commercial Partial 12/18/2003
Correction
Partial Correction
12/18/2003
None PARTIALGRID 1-2 CTO D
Underslab Electrical Inspection - Commercial Partial 12/18/2003
Correction
Partial Correction
12/18/2003
None UNDER SLAB ELET. CONDUIT GENERATOR ROOM
Footing Inspection - Commercial Partial 12/19/2003
Correction
Partial Correction
12/19/2003
FOOTINGS @ RETAINING WALL S/SW OF BLDG OK TO POUR WHEN READY PER SECT 18/S1.6 SEGMENT RW1;
Underground Plumbing Inspection - Commercial Partial 12/19/2003
Correction
Resolved
12/19/2003
U.G. STORM DRAIN PIPING E-W BRANCH ALONG (2.8) WEST OF (D) PROCEEDING N TO (3.1) +
Correction
Resolved
12/19/2003
U.G. SANITARY SEWER PIPING THRU GRADE BEAM @ D/2.2 THEN NORTH TO (3)
Correction
Partial Correction
12/19/2003
STORM DRAIN PIPING W OF (D) AT/NEAR MANHOLE PRESSURE TEST & VISUAL OK
Correction
Resolved
12/19/2003
U.G. SANITARY PIPING 20 FEET 6 IN C. I. NOTRH TO 4 LINE TURNING EAST UNDER GRADE BEAM 10 FEET PARALLEL TO 4 LINE PRESSURE TEST AND VISUAL
Underground Electrical Inspection - Commercial Partial 12/22/2003
Correction
Partial Correction
12/22/2003
LIGHTNING PROTECTION BONDING CONDUCTOR STRAPPED TO 6" C.I. SAN W OF (4)/(D)
Underground Plumbing Inspection - Commercial Passed 12/22/2003
Correction
Resolved
12/22/2003
STORM DRAIN PIPING W OF (D) AT/NEAR MANHOLE
Correction
Resolved
12/22/2003
U.G. SANITARY PIPING 20 FEET 6 IN C. I. NOTRH TO 4 LINE TURNING EAST UNDER GRADE BEAM 10 FEET PARALLEL TO 4 LINE; 6" C. I. W OF (D) FROM (4) NORTH TO (6) PRESSURE TEST AND VISUAL
Footing Inspection - Commercial Partial 12/23/2003
Correction
Resolved
12/23/2003
None
Correction
Resolved
12/23/2003
None
Correction
Resolved
12/23/2003
EXTERIOR WALL FOOTING
Correction
Resolved
12/23/2003
INTERIOR COLUMN FOOTINGS
Correction
Resolved
12/23/2003
EXTERIOR WALL GRADE BEAM
Correction
Resolved
12/23/2003
EXTERIOR WALL GRADE BEAM
Correction
Resolved
12/23/2003
INTERIOR GRADE BEAMS
Correction
Resolved
12/23/2003
MEZZANINE COLUMN FOOTINGS
Correction
Partial Correction
12/23/2003
FOOTINGS @ RETAINING WALL S/SW OF BLDG SEGMENT RW1; SEGMENT RW2; PER SECT 18/S1.6 OK TO POUR WHEN READY
Retaining Wall Inspection Partial 12/29/2003
Correction
Partial Correction
12/29/2003
WALL SEGMENT RW1 LOWER 20` LIFT WITH ELECT CONDUIT/BOXES; RE-BAR; FORMWORK OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 12/30/2003
Correction
Partial Correction
12/30/2003
FOOTINGS @ RETAINING WALL S/SW OF BLDG SEGMENTS RW1; RW2; RW3; PER SECT 18/S1.6 OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 01/02/2004
Correction
Partial Correction
01/02/2004
INTERIOR COLUMN FOOTINGS G5(F2) PIER AND H4 (F4) PIERS APPROVED
Piers/Caissons Inspection - Commercial Partial 01/02/2004
Correction
Partial Correction
01/02/2004
None DRILLED PIERS P6/P6 AT LOCATIONS: 21A,23A,26,27,28,29,30,31,32,33 APPROVED NE TUNNEL ROOF DECK FROM 200 TO 240
Retaining Wall Inspection Passed 01/08/2004
Correction
Resolved
01/08/2004
WALL SEGMENT RW1 LOWER 20` LIFT WITH ELECT CONDUIT/BOXES; UPPER 12` LIFT; RE-BAR; FORMWORK OK TO POUR WHEN READY
Retaining Wall Inspection Not Ready 01/12/2004
Correction
Corrective Action Required
01/12/2004
WALL SEGMENT RW2 REQUEST INSPECTION WHEN ONE FACE FORMS ARE IN PLACE AND CONSTRUCTION JOINT SURFACE IS PREPARED. INSIDE FACE FORMWORK IN PROGRESS
Retaining Wall Inspection Partial 01/13/2004
Correction
Resolved
01/13/2004
WALL SEGMENT RW1 LOWER 20` LIFT; UPPER 12` LIFT; RE-BAR; FORMWORK WITH ELECT CONDUIT/BOXES
Correction
Partial Correction
01/13/2004
WALL SEGMENT RW2 LOWER LIFT TO 570 CM; OK TO POUR WHEN READY W/ EL COND/BOXES/SLEEVES
Foundation Inspection - Commercial Partial 01/15/2004
Correction
Partial Correction
01/15/2004
TUNNEL SLAB OK TO COVER C BLDG 3.5 TO 5 LINE
Correction
Partial Correction
01/15/2004
TUNNEL SLAB OK TO COVER C/D TUNNEL 5.5 TO D 2.2
Foundation Inspection - Commercial Partial 01/16/2004
Correction
Partial Correction
01/16/2004
TUNNEL SLAB OK TO COVER C/D TUNNEL 5.5 TO D3.8
Retaining Wall Inspection Partial 01/21/2004
Correction
Partial Correction
01/21/2004
WALL SEGMENT RW2 LOWER LIFT TO 570 CM; UPPER LIFT; WHEN SETTING FORMS ENSURE KEYWAY IS CLEAR/CLEAN AND WATERSTOP IS CLEAN & PROPERLY POSITIONED. OK TO POUR WHEN READY W/ EL COND/BOXES/SLEEVES
Underslab Plumbing Inspection - Commercial Partial 02/05/2004
Correction
Resolved
02/05/2004
None AIR TEST APPROVED B BLDG--ALL
Foundation Inspection - Commercial Passed 02/12/2004
Correction
Resolved
02/12/2004
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS ON (A) FRM (7) S TO (1) ON (1) FRM (A) W TO (C)
Correction
Resolved
02/12/2004
INTERIOR COLUMNS D/3; B/2; C/2; D/2; D/1 B/6; C/6; 5/B; 5/C; 5/D; B/4; C/4; D/4; B/3; C/3;
Correction
Resolved
02/12/2004
TUNNEL SLAB C BLDG 3.5 TO 5 LINE
Correction
Resolved
02/12/2004
TUNNEL SLAB C/D TUNNEL 5.5 TO D3.8
Correction
Resolved
02/12/2004
UNDERGROUND FUEL TANK SLAB IN PLACE OK TO POUR WHEN READY REINF BAR + HOLD-DOWNS
Foundation Inspection - Commercial Partial 02/17/2004
Correction
Partial Correction
02/17/2004
SWITCHGEAR VAULT PER ASI #20 OK TO POUR WHEN READY REV DRWG XS-76 + 15/S1.6 BOTTOM SLAB
Retaining Wall Inspection Partial 02/18/2004
Correction
Partial Correction
02/18/2004
WALL SEGMENT RW3 LOWER LIFT; WHEN SETTING FORMS ENSURE KEYWAY IS CLEAR/CLEAN AND WATERSTOP IS CLEAN & PROPERLY POSITIONED. OK TO POUR WHEN READY W/ EL COND/BOXES/SLEEVES
Correction
Resolved
02/18/2004
WALL SEGMENT RW2 UPPER LIFT W/ EL COND/BOXES/SLEEVES LOWER LIFT TO 570 CM
Foundation Inspection - Commercial Partial 02/19/2004
Correction
Partial Correction
02/19/2004
SWITCHGEAR VAULT PER ASI #20 WALLS PER REV DRWG XS-77 + 15/S1.6 OK TO POUR WHEN READY REV DRWG XS-76 + 15/S1.6 BOTTOM SLAB
Underground Plumbing Inspection - Commercial Partial 02/19/2004
Correction
Partial Correction
02/19/2004
PIPING @ PUMP STATION 6" C.I. PIPE LAID, JOINED, GROUTED OUTSIDE BETWEEN WETWELL, VALVE VAULT & METER M.H.
Retaining Wall Inspection Partial 02/26/2004
Correction
Partial Correction
02/26/2004
WALL SEGMENT RW3 LOWER LIFT; UPPER LIFT; WHEN SETTING FORMS ENSURE KEYWAY IS CLEAR/CLEAN AND WATERSTOP IS CLEAN & PROPERLY POSITIONED. OK TO POUR WHEN READY W/ EL COND/BOXES/SLEEVES
Underground Electrical Inspection - Commercial Partial 02/27/2004
Correction
Partial Correction
02/27/2004
GROUNDING RING GROUND RODS @ E WALL S END + CENTER W/ CONDUCTOR CLAMPED @ EACH ROD; PROTECT RODS & CONDUCTOR DURING BACKFILL OPS
Retaining Wall Inspection Not Ready 03/01/2004
Correction
Resolved
03/01/2004
WALL SEGMENT RW3
Correction
Corrective Action Required
03/01/2004
WALL SEGMENT RW4 NOT READY FOR INSPECTION
Retaining Wall Inspection Partial 03/02/2004
Correction
Partial Correction
03/02/2004
WALL SEGMENT RW4 ENSURE WATER STOP IS CLEAN & PROPERLY PLACED PRIOR TO POUR. OK TO POUR WHEN READY W/ EL COND/BOXES/SLEEVES FORM PANELS IN PROGRESS
Footing Inspection - Commercial Passed 03/03/2004
Correction
Resolved
03/03/2004
FOOTINGS @ RETAINING WALL S/SW OF BLDG SEGMENTS RW1; RW2; RW3; RW4; RW5; PER SECT 18/S1.6 OK TO POUR WHEN READY
Correction
Resolved
03/03/2004
INTERIOR COLUMN FOOTINGS
Underground Electrical Inspection - Commercial Partial 03/08/2004
Correction
Partial Correction
03/08/2004
GROUNDING RING GROUND RODS @ E WALL S END + N END + CENTER W/ CONDUCTOR CLAMPED @ EACH ROD; PROTECT RODS & CONDUCTOR DURING BACKFILL OPS
Retaining Wall Inspection Partial 03/09/2004
Correction
Resolved
03/09/2004
WALL SEGMENT RW5 VERTICAL WATER STOP REPLACEMENT OK IF APPROVED BY A/E W/ EL COND/BOXES/SLEEVES VERIFY V1 BARS ARE #5
Footing Inspection - Commercial Passed 03/11/2004
Correction
Resolved
03/11/2004
FOOTINGS @ RETAINING WALL S/SW OF BLDG SEGMENTS RW1; RW2; RW3; RW4; RW5; BOTH SEGMENTS RW6 PER SECT 17 & 18/S1.6 OK TO POUR WHEN READY
Retaining Wall Inspection Passed 03/15/2004
Correction
Resolved
03/15/2004
WALL SEGMENT RW1
Correction
Resolved
03/15/2004
WALL SEGMENT RW2
Correction
Resolved
03/15/2004
WALL SEGMENT RW6 ENSURE WATER STOP IS CLEAN & PROPERLY PLACED PRIOR TO POUR. OK TO POUR WHEN READY W/ EL COND/BOXES/SLEEVES FORM PANELS IN PROGRESS
Correction
Resolved
03/15/2004
WALL SEGMENT RW4
Correction
Resolved
03/15/2004
WALL SEGMENT RW5
Retaining Wall Inspection Passed 03/19/2004
Correction
Resolved
03/19/2004
None 35 FOOT CONNECTION FROM A BLDG TO CONTROL JOINT AT NORTH OF B BLDG TUNNEL/RW SEGMENT
Footing Inspection - Commercial Passed 03/26/2004
Correction
Resolved
03/26/2004
FOOTINGS @ RETAINING WALL S/SW OF BLDG SEGMENTS RW1; RW2; RW3; RW4; RW5; BOTH SEGMENTS RW6 PER SECT 17 & 18/S1.6
Correction
Resolved
03/26/2004
COLUMN FOOTINGS @ COOLING TOWERS OK TO POUR WHEN READY 12 PER SECT 11/S1.6 RE-BAR NEARING COMPLETION
Footing Inspection - Commercial Passed 03/31/2004
Correction
Resolved
03/31/2004
FOOTINGS @ RETAINING WALL S/SW OF BLDG
Correction
Resolved
03/31/2004
COLUMN FOOTINGS @ COOLING TOWERS
Correction
Resolved
03/31/2004
GRADE BEAMS @ COOLING TOWERS OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Passed 04/02/2004
Correction
Resolved
04/02/2004
CIP CONC COLUMNS @ COOLING TOWERS ANCHOR BOLTS TO BE HUNG. OK TO POUR WHEN READY. RE-BAR IN PLACE FORMWORK IN PROGRESS
Underslab Electrical Inspection - Commercial Partial 04/12/2004
Correction
Resolved
04/12/2004
UNDER-SLAB CONDUIT UNDER GRADE BEAM @ (D)/(5.3) TO 5` O/S WEST WALL 4"SCH 40 PVC (5) TO (6) x (B) TO (D)
Correction
Resolved
04/12/2004
None UNDER SLAB ELET. CONDUIT GENERATOR ROOM
Correction
Partial Correction
04/12/2004
U/S CONDUIT & GROUNDING @ COOLING TOWER AREA CONDUIT ONLY EAST OF (D)
Underground Plumbing Inspection - Commercial Partial 04/12/2004
Correction
Resolved
04/12/2004
PIPING @ PUMP STATION 6" C.I. PIPE LAID, JOINED, GROUTED OUTSIDE BETWEEN WETWELL, VALVE VAULT & METER M.H.
Correction
Partial Correction
04/12/2004
TWO 3" O2 LINES FROM TANK ENCLOSURE TO BLDG ENTRY EXTENDED PRESSURE TEST IN PROGRESS
Miscellaneous Inspection Passed 04/12/2004
Foundation Inspection - Commercial Partial 04/13/2004
Correction
Resolved
04/13/2004
UNDERGROUND FUEL TANK SLAB
Correction
Partial Correction
04/13/2004
SWITCHGEAR VAULT PER ASI #20 WALLS PER REV DRWG XS-77 + 15/S1.6 REV DRWG XS-76 + 15/S1.6 BOTTOM SLAB
Correction
Resolved
04/13/2004
PERIMETER FOUNDATION WALL @ OXYGEN TANK SLAB E & N BOUNDARIES
Suspended Slab Inspection Failed 04/14/2004
Correction
Corrective Action Required
04/14/2004
TOP SLAB OF ELECTRICAL VAULT POURED WITHOUT APPROVAL
Suspended Slab Inspection Passed 04/15/2004
Correction
Resolved
04/15/2004
TOP SLAB OF ELECTRICAL VAULT
Underslab Electrical Inspection - Commercial Passed 04/20/2004
Correction
Resolved
04/20/2004
U/S CONDUIT & GROUNDING @ COOLING TOWER AREA WEST COOLING TOWERS AREA - SECOND/FINAL SLAB POUR OK WHEN READY. LIGHTNING PROTECTION, GROUNDING, & CONDUIT
Underground Electrical Inspection - Commercial Partial 04/23/2004
Correction
Resolved
04/23/2004
LIGHTNING PROTECTION BONDING CONDUCTOR
Correction
Resolved
04/23/2004
GROUNDING RING
Correction
Partial Correction
04/23/2004
FEEDER CONDUIT TO PUMP STATION 2-1/2 PVC FRM W SIDE P.S. TO N OF SWITCHGEAR VAULT
Footing Inspection - Commercial Partial 05/11/2004
Correction
Partial Correction
05/11/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALONG (13) FROM (D`) TO (C`.3); ALONG (D`) FROM (13) TO (11.3); REBAR COVERAGE @ >= 3" OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 05/12/2004
Correction
Partial Correction
05/12/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALONG (13) FROM (D`) TO (C`.3); ALONG (D`) FROM (13) TO (11.3); ALONG (13) FROM (C`.3) TO (A`.7); REBAR COVERAGE @ >= 3" OK TO POUR WHEN READY
Underground Plumbing Inspection - Commercial Partial 05/12/2004
Correction
Resolved
05/12/2004
U.G. STORM DRAIN PIPING FROM D/1 10' N + 8" E
Correction
Resolved
05/12/2004
TWO 3" O2 LINES FROM TANK ENCLOSURE TO BLDG ENTRY
Correction
Partial Correction
05/12/2004
GREASE INTERCEPTOR OK TO COVER WHEN READY PER DRWG P1 REV /2\ PER PR6
Footing Inspection - Commercial Partial 05/17/2004
Correction
Partial Correction
05/17/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALONG (13) FROM (D`) TO (C`.3); ALONG (D`) FROM (13) TO (11.3); ALONG (13) FROM (C`.3) TO (A`.7); ALONG 13 FROM (A`.7) TO (A`) THEN S ALONG (A`) TO (12.3); REBAR COVERAGE @ >= 3" OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 05/20/2004
Correction
Resolved
05/20/2004
GRADE BEAMS @ COOLING TOWERS
Correction
Partial Correction
05/20/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALONG (13) FRM (D`) TO (C`.3); ALONG (D`) FRM (13) TO (11.3); ALONG (13) FRM (C`.3) TO (A`.7); ALONG 13 FRM (A`.7) TO (A`) THEN S ALONG (A`) TO (12.3); ALONG (A`) & (A) FROM (12.3) TO (7); ENSURE 3" REBAR COVERAGE OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 06/08/2004
Correction
Partial Correction
06/08/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; @ ALT #2 AREA OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 06/14/2004
Correction
Partial Correction
06/14/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; @ ALT #2 AREA OK TO POUR WHEN READY
Correction
Partial Correction
06/14/2004
ELEVATOR PIT SLABS ENSURE HOLE IS DRY AND REBAR COVERAGE IS >= 3" TO BANKS & BOTTOMS. ENSURE SUMPS ARE PER STATE ELEVATOR INSPECTOR REQUIREMENTS. SOUTH PIT OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 06/16/2004
Correction
Partial Correction
06/16/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; @ ALT #2 AREA OK TO POUR WHEN READY
Correction
Partial Correction
06/16/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALONG (13) FRM (D`) TO (C`.3); ALONG (D`) FRM (13) TO (11.3); ALONG (13) FRM (C`.3) TO (A`.7); ALONG 13 FRM (A`.7) TO (A`) THEN S ALONG (A`) TO (12.3); ALONG (A`) & (A) FROM (12.3) TO (7);
Correction
Partial Correction
06/16/2004
ELEVATOR PIT SLABS ENSURE HOLE IS DRY. ENSURE SUMPS ARE PER STATE ELEVATOR INSPECTOR REQUIREMENTS. SOUTH & NORTH PITS OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 06/18/2004
Correction
Partial Correction
06/18/2004
ELEVATOR PIT WALLS SOUTH ELEVATOR PIT OK TO POUR WHEN READY
Water Service Inspection Partial 06/24/2004
Correction
Partial Correction
06/24/2004
DOMESTIC SERVICE LINE VISUAL & PRESSURE TEST OK METER PIT NOT APPROVED UNTIL ACCEPTED BY LS PUBLIC WORKS & WATER UTILITIES FROM BUILDING ENTRY TO METER PIT
Foundation Inspection - Commercial Partial 06/25/2004
Correction
Partial Correction
06/25/2004
ELEVATOR PIT WALLS INCLUDING GRADE BEAM INTERFACE @ W WALL OF N PIT SOUTH & NORTH PIT WALLS OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 06/28/2004
Correction
Partial Correction
06/28/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; C/9.5; C`/10.5; @ ALT #2 AREA OK TO POUR WHEN READY
Correction
Resolved
06/28/2004
ELEVATOR PIT SLABS SOUTH & NORTH PITS
Footing Inspection - Commercial Partial 07/01/2004
Correction
Partial Correction
07/01/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; C/9.5; C`/10.5; A.1/12; @ ALT #2 AREA OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 07/02/2004
Correction
Resolved
07/02/2004
INTERIOR GRADE BEAMS
Correction
Partial Correction
07/02/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; C/9.5; C`/10.5; A.1/12; A.1/8; @ ALT #2 AREA OK TO POUR WHEN READY
Correction
Partial Correction
07/02/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALONG (13) FRM (D`) TO (C`.3); ALONG (D`) FRM (13) TO (11.3); ALONG (13) FRM (C`.3) TO (A`.7); ALONG 13 FRM (A`.7) TO (A`) THEN S ALONG (A`) TO (12.3); ALONG (A`) & (A) FROM (12.3) TO (7); ALONG (A.1) FROM (13) TO (8) + ~10` TO COMPLETE E-W ALONG (13); ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Correction
Resolved
07/02/2004
ELEVATOR PIT SLABS
Footing Inspection - Commercial Partial 07/07/2004
Correction
Partial Correction
07/07/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; C/9.5; C`/10.5; A.1/12; A.1/8; @ ALT #2 AREA
Correction
Partial Correction
07/07/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALNG (D`) FRM (13) TO (11.3); ALNG (13) FRM (C`.3) TO (A`.7); ALNG 13 FRM (A`.7) TO (A`) THEN S ALNG (A`) TO (12.3); ALNG (A`) & (A) FRM (12.3) TO (7); ALNG (A.1) FRM (13) TO (8) + ~10` TO COMPLETE E-W ALNG (13); ALONG (A.1) FROM (7) TO (9.5); OK TO POUR WHEN READY (13) FRM (D`) TO (C'.3);
Underslab Plumbing Inspection - Commercial Partial 07/07/2004
Correction
Partial Correction
07/07/2004
UNDERSLAB SANITARY LINE FROM 3.3 TO 4.5 -- C.I. 2/3/4 IN BRANCH AND MAIN WEST FROM A TO B LINE; ALONG (C.7`) N OF (10) + BRANCHES + TO 25 W OF W WALL VISUAL OK;
Correction
Resolved
07/07/2004
UNDER-SLAB SANITARY DRAIN LINE FROM (2.1) TO (1.4); ALL REMAINING FROM (1) TO (3) EXCEPT ALONG (C.7) BETWEEN (1) & (2) (2) TO (3) x (A.4) TO (B) + N-S ALONG A.8
Correction
Resolved
07/07/2004
None PARTIALGRID 1-2 CTO D
Underslab Plumbing Inspection - Commercial Partial 07/08/2004
Correction
Partial Correction
07/08/2004
UNDER-FLOOR ROOF DRAIN PIPING 12" BLDG STORM DRAIN FROM (D`) 10` E + 26` W; ENERGY CENTER COMPLETE ALT A BELOW:
Correction
Partial Correction
07/08/2004
UNDERSLAB SANITARY LINE ALONG (C.7`) N OF (10) + BRANCHES + TO 25 W (D`) VISUAL + PRESSURE TEST OK; ENERGY CENTER COMPLETE ALT A BELOW:
Footing Inspection - Commercial Partial 07/08/2004
Correction
Resolved
07/08/2004
INTERIOR GRADE BEAMS W OF N ELEVATOR BANK OK TO POUR WHEN READY PERIMETER OF STAIRWELL
Correction
Resolved
07/08/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALNG (D`) FRM (13) TO (11.3); ALNG (13) FRM (C`.3) TO (A`.7); ALNG 13 FRM (A`.7) TO (A`) THEN S ALNG (A`) TO (12.3); ALNG (A`) & (A) FRM (12.3) TO (7); ALNG (A.1) FRM (13) TO (8) + ~10` TO COMPLETE E-W ALNG (13); ALONG (A.1) FROM (7) TO (9.5); (13) FRM (D`) TO (C'.3);
Underground Electrical Inspection - Commercial Partial 07/09/2004
Correction
Partial Correction
07/09/2004
LIGHT POLE BASES WHEN READY; GROUNDING NOT READY FOR INSPECTION #33; #34; #35 OK TO POUR BASES
Underslab Plumbing Inspection - Commercial Partial 07/09/2004
Correction
Partial Correction
07/09/2004
UNDERSLAB SANITARY LINE ALONG (C.7`) N OF (10) + BRANCHES + TO 25 W (D`) VISUAL + PRESSURE TEST OK; ALONG (A.4) FRM (7.3) TO (8.3) VISUAL OK; ENERGY CENTER COMPLETE ALT A BELOW:
Footing Inspection - Commercial Partial 07/13/2004
Correction
Resolved
07/13/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION ALNG (13) FRM (C`.3) TO (A`.7); ALNG 13 FRM (A`.7) TO (A`), S ALNG (A`) TO (12.3); ALNG (A`) & (A) FRM (12.3) TO (7); ALNG (A.1) FRM (13) TO (8) + ~10` TO COMPL E-W ALNG (13); ALONG (A.1) FROM (7) TO (9.5); COL FTG D`/11 + TIE G.B. TO N; (13) FRM (D`) TO (C'.3); (D`) FRM (13) TO (11);
Underslab Plumbing Inspection - Commercial Partial 07/13/2004
Correction
Partial Correction
07/13/2004
UNDER-FLOOR ROOF DRAIN PIPING 12" BLDG STORM DRAIN FROM (D`) 10` E + 26` W; TRUNK LINE ALONG (11) VISUAL; ENERGY CENTER COMPLETE ALT A BELOW:
Correction
Partial Correction
07/13/2004
UNDERSLAB SANITARY LINE ALONG (C.7`) N OF (10) + BRANCHES + TO 25 W (D`) VISUAL + PRESSURE TEST OK; ALONG (A.4) FRM (7.3) TO (8.3); ALL W OF (A.8) SUBSTANTIALLY COMPLETE & TESTED; ENERGY CENTER COMPLETE ALT A BELOW:
Underslab Plumbing Inspection - Commercial Passed 07/15/2004
Correction
Resolved
07/15/2004
UNDER-FLOOR ROOF DRAIN PIPING ALL ROOF DRAIN PIPING NOW COMPLETE & TESTED ENERGY CENTER COMPLETE ALT A BELOW:
Correction
Resolved
07/15/2004
UNDERSLAB SANITARY LINE ALL SANITARY PIPING NOW COMPLETE & TESTED ENERGY CENTER COMPLETE ALT A BELOW:
Underground Electrical Inspection - Commercial Partial 07/15/2004
Correction
Partial Correction
07/15/2004
LIGHT POLE BASES #33; 34; 35; 1; 2; 6;7 WHEN READY GROUNDING APPROVED ONLY ON #2 OK TO POUR BASES
Underground Electrical Inspection - Commercial Partial 07/16/2004
Correction
Partial Correction
07/16/2004
LIGHT POLE BASES #33; 34; 35; 1; 2; 6;7; OK TO POUR BASES + GROUNDING APPROVED
Footing Inspection - Commercial Partial 07/20/2004
Correction
Resolved
07/20/2004
INTERIOR GRADE BEAMS PERIMETER OF STAIRWELL W OF N ELEVATOR BANK
Correction
Resolved
07/20/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION (13) FRM (C`.3) TO (A`.7); (13) FRM (A`.7) TO (A`), S ALNG (A`) TO (12.3); ALNG (A`) & (A) FRM (12.3) TO (7); ALNG (A.1) FRM (13) TO (8) + ~10` TO COMPL E-W ALNG (13); (A.1) FRM (7) TO (9.5); COL FTG D`/11 + TIE G.B. TO (N); CLOSE (D) FRM (6) TO (10) (13) FRM (D`) TO (C'.3); (D`) FRM (13) TO (11);
Footing Inspection - Commercial Passed 07/21/2004
Correction
Resolved
07/21/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; C/9.5; C`/10.5; A.1/12; A.1/8; C/8 RE-CONSTRUCT @ ALT #2 AREA OK TO POUR WHEN READY
Underground Electrical Inspection - Commercial Partial 07/23/2004
Correction
Resolved
07/23/2004
LIGHT POLE BASES
Correction
Partial Correction
07/23/2004
LIGHT POLE BASES #33; 34; 35; 1; 2; 6;7; OK TO POUR BASES + GROUNDING APPROVED
Correction
Resolved
07/23/2004
PARKING LOT/DRIVE LIGHT POLE BASES + U.G. FEEDER CONDUIT
Correction
Resolved
07/23/2004
FEEDER CONDUIT TO PUMP STATION
Footing Inspection - Commercial Partial 08/17/2004
Correction
Resolved
08/17/2004
INTERIOR GRADE BEAMS
Correction
Resolved
08/17/2004
INTERIOR COLUMN FOOTINGS B`/12; C`/12; B/8; A.8/9.5; B.8/9.5; A.8/10.5; B.8/10.5; C/9.5; C`/10.5; A.1/12; A.1/8; C/8 RE-CONSTRUCT @ ALT #2 AREA
Correction
Resolved
08/17/2004
GRADE BEAM + INTEGRAL COLUMN FOOTINGS - "A" EXTENSION
Correction
Partial Correction
08/17/2004
WALL FOOTINGS @ TRUCK DOCK E 10' OF RAMP WALL FTGS @ N & S; OK TO POUR WHEN READY DOCK(E) WALL FOOTING +
Footing Inspection - Commercial Partial 08/19/2004
Correction
Partial Correction
08/19/2004
WALL FOOTINGS @ TRUCK DOCK E 10' OF RAMP WALL FTGS @ N & S; REMAINDER OF RAMP WALL FTG @ S; OK TO POUR WHEN READY DOCK(E) WALL FOOTING +
Footing Inspection - Commercial Partial 09/02/2004
Correction
Resolved
09/02/2004
WALL FOOTINGS @ TRUCK DOCK E 10' OF RAMP WALL FTGS @ N & S; REMAINDER OF RAMP WALL FTG @ S; OK TO POUR WHEN READY DOCK(E) WALL FOOTING +
Correction
Partial Correction
09/02/2004
None PER S7.O DET 14 ETAL S7.3 OK TO COVER CLEAN SOUTH FOOTING PRIOR TO FORMING/INSPECTION DOCK WALL "a" BALANCE OF NORTH WALL FTG
Retaining Wall Inspection Partial 09/14/2004
Correction
Partial Correction
09/14/2004
TRUCK DOCK RAMP WALLS SOUTH DOCK WALL PARTIAL; OK TO POUR WHEN READY
Footing Inspection - Commercial Partial 09/15/2004
Correction
Resolved
09/15/2004
GRADE BEAM @ C/L (D) FROM (13) TO (14) APPROVED 9/13/04
Footing Inspection - Commercial Partial 09/22/2004
Correction
Resolved
09/22/2004
WALL FOOTINGS @ TRUCK DOCK
Correction
Resolved
09/22/2004
None DOCK WALL "a" BALANCE OF NORTH WALL FTG
Correction
Resolved
09/22/2004
GRADE BEAM @ C/L (D) FROM (13) TO (14)
Correction
Partial Correction
09/22/2004
DOCK LEVELER PIT SLABS ENSURE RE-BAR COVERAGE OK TO POUR WHEN READY
Rough Framing Inspection - Commercial Passed 09/22/2004
Correction
Resolved
09/22/2004
CIP CONC COLUMNS @ COOLING TOWERS
Footing Inspection - Commercial Passed 09/24/2004
Correction
Resolved
09/24/2004
DOCK LEVELER PIT SLABS
Correction
Resolved
09/24/2004
CONC GRADE BEAM N & S OF TRUCK DOCK HEAD WALL OK TO POUR WHEN READY
Foundation Inspection - Commercial Partial 10/29/2004
Correction
Resolved
10/29/2004
BASEMENT WALLS INCLUSIVE OF INTEGRAL COLUMNS
Correction
Resolved
10/29/2004
INTERIOR COLUMNS
Correction
Resolved
10/29/2004
TUNNEL SLAB
Correction
Resolved
10/29/2004
TUNNEL SLAB
Correction
Resolved
10/29/2004
UNDERGROUND FUEL TANK SLAB
Correction
Resolved
10/29/2004
SWITCHGEAR VAULT PER ASI #20
Correction
Resolved
10/29/2004
PERIMETER FOUNDATION WALL @ OXYGEN TANK SLAB
Correction
Resolved
10/29/2004
ELEVATOR PIT WALLS
Correction
Partial Correction
10/29/2004
TRUCK WELL TRENCH DRAIN POUR PREP OK TO POUR WHEN READY
Retaining Wall Inspection Passed 11/04/2004
Correction
Resolved
11/04/2004
WALL SEGMENT RW6
Correction
Resolved
11/04/2004
None
Correction
Resolved
11/04/2004
TRUCK DOCK RAMP WALLS
Foundation Inspection - Commercial Passed 11/04/2004
Correction
Resolved
11/04/2004
TRUCK WELL TRENCH DRAIN
Water Service Inspection Passed 11/04/2004
Correction
Resolved
11/04/2004
DOMESTIC SERVICE LINE VISUAL & PRESSURE TEST OK METER PIT NOT APPROVED UNTIL ACCEPTED BY LS PUBLIC WORKS & WATER UTILITIES FROM BUILDING ENTRY TO METER PIT
Underground Electrical Inspection - Commercial Passed 11/04/2004
Correction
Resolved
11/04/2004
LIGHT POLE BASES #33; 34; 35; 1; 2; 6;7; GROUNDING APPROVED
Underground Plumbing Inspection - Commercial Passed 11/04/2004
Correction
Resolved
11/04/2004
GREASE INTERCEPTOR PER DRWG P1 REV /2\ PER PR6
Piers/Caissons Inspection - Commercial Passed 11/04/2004
Correction
Resolved
11/04/2004
None
Final Inspection - Commercial Passed 11/04/2004
Correction
Resolved
11/04/2004
CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.