Summary
B0300530
Building Permit - Commercial
Certificate of Occupancy
JUNIOR COLLEGE DISTRICT OF
ALTERATION COMMERCIAL
STUDENT SERVICES TENANT FINISH
04/01/2003
05/15/2003
11/11/2003
08/19/2003
Locations
Contacts
CDFM2, Address:JOHN GAAR  
METROPOLITAN COMMUNITY COLLEGES, Address:3217 BROADWAY SUITE 306  
JUNIOR COLLEGE DISTRICT OF, Address:3200 BROADWAY  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 09/28/2003 10/29/2010
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - 2000 IBC 708.6. - Openings. Openings in fire partitions shall be protected in accordance with Section 714.
Correction

CA - Detail D10 on Sheet A400 indicates that a modification will be made to the fire shutters.
Correction

CA - Detail A-10 on Sheet A400 does not indicate how the integrity of the rated wall will be maintained.
Correction

Fire Department; Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Documents shall bear a State of Missouri architect/engineers seal..Construction documents shall include, but not be limited to, all of the following: 1. A floor plan. 2. Locations of alarm-initiating and notification appliances.
Correction

Fire Department-Egress doors shall be readily openable from the egress side without the use of a key or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Each layer of fire-resistive assemblies shall be inspected and approved prior to the application of additional layers or finishes. All firestopping of penetrations and required dampers shall be inspected and approved prior to concealing.
Correction

CA - 2000 IBC 1109.1 - Required accessible elements shall be identified by the International Symbol of Accessiblity at the locations listed in Section 1109.1. 1. Not applicable as the zoning ordinance is more restrictive. 2. Accessible passenger loading zones. 3. Accessible areas of refuge required by Section 1103.2.13.5. 4. Accessible rooms where multi single-user toilet or bathing rooms are clustered at a single location. 5. Accessible entrances where not all entrances are accessible. 6. Accessible check-out aisles where not all aisles are accessible. The sign, where provided, shall be above the check-out aisle in the same location as the check-out aisle number or type of check-out identification. 7. Unisex toilet and bathing rooms. 8. Accessible dressing, fitting, and locker rooms where not all such rooms are accessible.
Correction

CA - 2000 IBC 1108.4 - Where kitchen, kitchenettes and wet bars are provided in accessible spaces or rooms, they shall be accessible in accordance with ICC/ANSI A117.1.
Correction

CA - 2000 IBC 2406.1 - Human impact loads. Individual glazed areas, including glass mirrors, in hazardous locations as devined in Section 2406.2 shall pass the test requirements of CPSC 16 CFR 1201, listed in Chapter 35. Glazing shall comply with the CSPC 16 CFR, Part 1201 criteria for Category I or Category II as indicated in Table 2406.1.
Correction

CA - 2000 IBC 803.4 - Interior finish requirements based on group. Interior wall and ceiling finish shall have a flame spread index not greater than that specified in Table 803.4 for the group and location designated.
Correction

CA - 2000 IBC 803.5.1 - Textile wall coverings. Textile wall coverings shall have a Class A flame spread index in accordance with ASTM E 84 and be protected by automatic sprinklers installed in accordance with Section 903.3.1.1 or Section 903.3.1.2 or the covering shall meet the criteria of Section 803.5.1.1 or Section 803.5.1.2 when tested in the manner intended for use in accordance with NFPA 265 using the product mounting system, including adhesive.
Correction

CA - 2000 IBC 715.2 - Installation. Fire dampers, smoke dampers, combination fire/smoke dampers and ceiling dampers located in air distribution and smoke-control systems shall be installed in accordance with the requirements of this section, the manufacturer's installation instructions and listings.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

Fire Department; Required means of egress components shall be maintained during construction and demolition.
Correction

Fire Department; Extension cords and flexible cords shall not be a substitute for permanent wiring. Extension cords and flexible cords shall not be affixed to structures, extended through walls, ceilings or floors, or under doors or floor cove-ings, nor shall such cords be subject to environmental damage or physical impact.
Correction

Fire Department; The required fire-resistance rating of fire-resistance-rated construction (including walls, fire stops, shaft enclosures, partitions and floors) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings, and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance rated assemblies shall be protected by self-closing or automatic- closing doors of approved construction meeting the fire protection requirements for the assembly.
Correction

Fire Department. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. The plans and specifications shall bear a State of Missouri licensed engineers seal. This includes fire sprinkler systems, grease hood and duct suppression systems as well as other fire suppression system.
Correction

Fire Department: Fire protection systems shall be maintained in accordance with the original installation standards for that system. Required fire protection systems shall be extended, altered, or augmented as necessary to maintain and continue pro-tection whenever the building is altered, remodeled or added to.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-7343.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $977.00 $977.00 Paid 05/15/2003
24 BLDG Plan Check Fees $36.25 $36.25 Paid 05/15/2003
25 Electrical Permit Fee $90.00 $90.00 Paid 05/15/2003
25 Mechanical Permit Fees $26.00 $26.00 Paid 05/15/2003
25 Plumbing Permit Fees $48.00 $48.00 Paid 05/15/2003
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Partial 06/19/2003
Correction
Partial Correction
06/19/2003
None WALLS ONLY - FRAMING AND ELECT. - ROOM NUMBERS 216, 213 EXCEPT SOUTH WALL OF THE BREAK AREA AND ENTRANCE DOOR. CORRIDOR 205 - CORRIDOR SIDE. ABOVE AREAS OK TO ROCK. FRAMING AND ELECT. APPROVED.
All Rough Inspection - Commercial Partial 06/24/2003
Correction
Partial Correction
06/24/2003
None IN WALL FOOM NUMBERS 211, 212, 213,206 AND BACK SIDE OF OPEN OFFICE 201 BACK SIDE OF OPEN OFFICE 234 FRAMING AND ELECT. APPROVED
Rough Plumbing Inspection - Commercial Passed 06/24/2003
Correction
Resolved
06/24/2003
None
All Rough Inspection - Commercial Partial 06/27/2003
Correction
Partial Correction
06/27/2003
None FRAMING AND ELECT. APPROVED ROOM NUMBERS 209, 211D, 211H, DOOR OPENING 210, DOOR OPENING 212, 210 H. WALLS ONLY.
Rough Plumbing Inspection - Commercial Passed 06/27/2003
Correction
Resolved
06/27/2003
None ROOM NUMBER- 213J ANDWEST WALL OF 217
All Rough Inspection - Commercial Partial 07/08/2003
Correction
Resolved
07/08/2003
None 1.FRAMING AND ELECT. SOFFIT AREA ROOM NUMBER 205 2. FRAMING APPROVED DOOR OPENING 213
Above Ceiling Inspection Failed 08/04/2003
Correction
Corrective Action Required
08/04/2003
LIGHT SUPPORT ROOM NUMBERS - 210, 210G, 208 ABC AND E.,209 217, SUITE 213, 213 A, K, J AND K, SUITE 216 A, B,C, AND D. ALL OF THE ABOVE ROOMS REQUIRES SUPPORT WIRES ON THE LIGHTS CAN LIGHTS ABOVE 217 APPROVED..
Erosion Control Inspection Residential Passed 08/04/2003
Above Ceiling Inspection Failed 08/07/2003
Correction
Resolved
08/07/2003
LIGHT SUPPORT
Correction
Corrective Action Required
08/07/2003
SUPPORT WIRES LIGHT FIXTURES ROOM 210 8 CAN LIGHTS - 205 OK TO INSTALL CEILING TILE THROUGHT EXCEPT LEAVE 1 TILE OUT IN ROOM 205 AND 210.
All Rough Inspection - Commercial Passed 08/07/2003
Correction
Resolved
08/07/2003
None WALLS ONLY - FRAMING AND ELECT. - ROOM NUMBERS 216, 213 EXCEPT SOUTH WALL OF THE BREAK AREA AND ENTRANCE DOOR. CORRIDOR 205 - CORRIDOR SIDE. ABOVE AREAS OK TO ROCK. FRAMING AND ELECT. APPROVED.
Correction
Resolved
08/07/2003
None IN WALL FOOM NUMBERS 211, 212, 213,206 AND BACK SIDE OF OPEN OFFICE 201 BACK SIDE OF OPEN OFFICE 234 FRAMING AND ELECT. APPROVED
Correction
Resolved
08/07/2003
None FRAMING AND ELECT. APPROVED ROOM NUMBERS 209, 211D, 211H, DOOR OPENING 210, DOOR OPENING 212, 210 H. WALLS ONLY.
All Rough Inspection - Commercial Passed 08/11/2003
Correction
Resolved
08/11/2003
None 1.FRAMING AND ELECT. SOFFIT AREA ROOM NUMBER 205 2. FRAMING APPROVED DOOR OPENING 213
Above Ceiling Inspection Passed 08/11/2003
Correction
Resolved
08/11/2003
SUPPORT WIRES
Occupancy Inspection - Codes Commercial Failed 08/11/2003
Correction
Corrective Action Required
08/11/2003
VESTIBULE DOORS VESTIBULE DOORS FAILED TO CLOSE
Correction
Corrective Action Required
08/11/2003
EXIT LIGHT REPAIR MAIN EXIT LIGHT
Correction
Corrective Action Required
08/11/2003
LABEL DOOR LABEL DOOR - NOT AN EXIT - CORRIDOR 216 D
Correction
Corrective Action Required
08/11/2003
SPRINKLER HEAD DROP SPRINKLER HEAD ROOM 208 C
Occupancy Inspection - Codes Commercial Passed 08/18/2003
Correction
Resolved
08/18/2003
EXIT LIGHT
Correction
Resolved
08/18/2003
VESTIBULE DOORS
Correction
Resolved
08/18/2003
Receive Planning & Development Approval OCCUPANCY APPROVED CLOSE PERMIT C. O.
Correction
Resolved
08/18/2003
LABEL DOOR
Correction
Resolved
08/18/2003
SPRINKLER HEAD
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home