Summary
B0300358
Building Permit - Commercial
Final Completion
LEES SUMMIT SCHOOL DIST R 7
ALTERATION COMMERCIAL
AREA "A" HIGH SCHOOL ALTERATIONS
03/11/2003
04/11/2003
10/08/2003
02/10/2004
Locations
Contacts
JE DUNN CONSTRUCTION CO., Address:929 HOLMES  
LEES SUMMIT SCHOOL DIST R 7, Address:600 MILLER  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 09/07/2003 10/29/2010
Correction

CA - ANSI A117.1-1998 404.2.7 - Door Hardware. Handles, pulls, latches, locks, and other operable parts on accessible doors shall have a shape that is easy to grasp with one hand and does not require tight grasping, pinching, or twisting of the wrist to operate. Such hardware shall be 34 inches minimum and 48 inches maximum above the floor or ground. Where sliding doors are in the fully open position, operating hardware shall be exposed and usable from both sides.
Correction

Fire Department; Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Documents shall bear a State of Missouri architect/engineers seal..Construction documents shall include, but not be limited to, all of the following: 1. A floor plan. 2. Locations of alarm-initiating and notification appli- ances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing informa- tion for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Correction

Fire Department- Egress doors shall be readily openable from the egress side without the use of a key or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
Correction

CA - Detailed information was not provided on the fire-shutter.
Correction

CA - Detailed information was not provided on the wheelchair lift to be installed in corridor 139.
Correction

CA - Detailed information was not provided on the inclined stair lift to be installed in stairway 152.
Correction

CA - It is not clearly indicated how the required exit path will be maintianed in stairway 152 with the installation of the chair lift.
Correction

CA - Openings created in fire-resistive construction from the demolition of the current M/E/P's shall be pathed by an approved means.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Each layer of fire-resistive assemblies shall be inspected and approved prior to the application of additional layers or finishes. All firestopping of penetrations and required dampers shall be inspected and approved prior to concealing.
Correction

CA - The Final Development Plan must be approved prior to issuing full building permits.
Correction

CA - 2000 IBC 1109.1 - Required accessible elements shall be identified by the International Symbol of Accessiblity at the locations listed in Section 1109.1. 1. Not applicable as the zoning ordinance is more restrictive. 2. Accessible passenger loading zones. 3. Accessible areas of refuge required by Section 1103.2.13.5. 4. Accessible rooms where multi single-user toilet or bathing rooms are clustered at a single location. 5. Accessible entrances where not all entrances are accessible. 6. Accessible check-out aisles where not all aisles are accessible. The sign, where provided, shall be above the check-out aisle in the same location as the check-out aisle number or type of check-out identification. 7. Unisex toilet and bathing rooms. 8. Accessible dressing, fitting, and locker rooms where not all such rooms are accessible.
Correction

CA - 2000 IBC 1003.3.1.6 - Thresholds. Thresholds at doorways shall not exceed 0.75 inch in height for sliding doors serving dwelling units or 0.5 inch for other doors. Raised thresholds and floor level changes greater then 0.25 inch at doorways shall be beveled with a slope not greater than one unit vertical in two units horizontal (50-percent slope).
Correction

CA - 2000 IBC 711.3 - Fire-resistance-rated walls. Penetrations into or through fire walls, fire barriers, smoke barrier walls, and fire partitions shall comply with this section.
Correction

CA - 2000 IBC 1109.3.3 - Other signs. At exits and elevators serving a required accessible space, but not providing an approved accessible means of egress, signs shall be installed indicating the location of accessible means of egress.
Correction

CA - 2000 IBC 1108.12.3 - Point of sales and service counters. Where counters are provided for sales or distribution of goods or services, at least one of each type provided shall be accessible. Where such counters are dispersed throughout the building or facility, the accessible counters shall also be dispersed.
Correction

Fire Department; Required means of egress components shall be maintained during construction and demolition.
Correction

Fire Department; Extension cords and flexible cords shall not be a substitute for permanent wiring. Extension cords and flexible cords shall not be affixed to structures, extended through walls, ceilings or floors, or under doors or floor cove-ings, nor shall such cords be subject to environmental damage or physical impact.
Correction

Fire Department; The required fire-resistance rating of fire-resistance-rated construction (including walls, fire stops, shaft enclosures, partitions and floors) shall be maintained. Such elements shall be properly repaired, restored or replaced when damaged, altered, breached or penetrated. Openings made therein for the passage of pipes, electrical conduit, wires, ducts, air transfer openings, and holes made for any reason shall be protected with approved methods capable of resisting the passage of smoke and fire. Openings through fire-resistance rated assemblies shall be protected by self-closing or automatic- closing doors of approved construction meeting the fire protection requirements for the assembly.
Correction

Fire Department: Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service main and all other fire protection systems and appurteances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the code official. The code official shall be notified before any required acceptance testing. NOTE: Acceptance testing shall be scheduled at least 48 hours in advance by calling (816) 969-7343.
Correction

Fire Department: Fire detection, alarm and extinguishing systems shall be maintained in an op-erative condition at all times, and shall be replaced or repaired where defective.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

CA - 2000 IMC 602.2.1 - Except as required by Section 602.2.1.1 through 602.2.1.4, materials exposed within plenumbs shall be noncombustible or shall have a flame spread index of not more than 25 and a smoke-developed index of not more than 50 when tested in accordance with ASTM E 84.
Correction

CA - 2000 IMC 606.2.2 - Common supply and return air systems. Where multiple air-handling systems share common supply or return air ducts or plenums with a combined design capacity greater than 2,000 cfm, the return air system shall be provided with smoke detectors in accordance with Section 606.2.1.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Correction

All backflow prevention assemblies must be tested and reports filed with the Lee's Summit Water Utilities Backflow Division (816-969-7636) within 30 days from the date installed.
Correction

Backflow prevention assembly must be located in an accessible location, min. 12" from floor, min. 6" from wall, max. 48" from floor.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $2,102.00 $2,102.00 Paid 04/11/2003
24 BLDG Plan Check Fees $55.00 $55.00 Paid 04/11/2003
25 Electrical Permit Fee $160.00 $160.00 Paid 04/11/2003
25 Mechanical Permit Fees $125.50 $125.50 Paid 04/11/2003
25 Plumbing Permit Fees $97.00 $97.00 Paid 04/11/2003
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Commercial Not Ready 04/17/2003
Correction
Corrective Action Required
04/17/2003
Blueprints NO APPROVED BLUEPRINTS ON SITE. DO NOT COVER. CALL FOR REINSPECTION.
Miscellaneous Inspection Failed 04/18/2003
Correction
Corrective Action Required
04/18/2003
DRAWING SHEET A2.1 MISSING FROM ON-SITE SET OF PERMIT DRAWINGS
Underslab Plumbing Inspection - Commercial Partial 04/18/2003
Correction
Resolved
04/18/2003
Blueprints
Correction
Partial Correction
04/18/2003
UNDER-FLOOR DWV PIPING SLOPED TO DRAIN. OK TO COVER WHEN READY. PHASE 1 (W 1/2) OF AREA A EXCAVATED; LAID; JOINED
Miscellaneous Inspection Failed 04/22/2003
Underslab Electrical Inspection - Commercial Partial 04/22/2003
Correction
Partial Correction
04/22/2003
CONDUIT & BOX INSTALLATION OK TO COVER WHEN READY TO RECEPT DESK RM 103 + TO CONF TABLE RM 106
Rough Plumbing Inspection - Commercial Partial 04/30/2003
Correction
Partial Correction
04/30/2003
None PHASE 1 BUILDING A ABOVE GROUND ROUGH PLUMBING APPROVED
All Rough Inspection - Commercial Failed 05/21/2003
Correction
Corrective Action Required
05/21/2003
IN-WALL SYSTEMS ROUGH SPOT-CHECKED. CHECK ALL; TIGHTEN AS NEEDED ELECTRICAL CONDUIT-BOX CONNECTIONS NOT TIGHT
All Rough Inspection - Commercial Partial 05/23/2003
Correction
Partial Correction
05/23/2003
IN-WALL SYSTEMS ROUGH LOWER LEVEL ONLY ELECT WORK ONLY APPROVED
Correction
Partial Correction
05/23/2003
CEILING DROP @ RECEP 103; L,G. STEEL STUD PARTITIONS WORKMANSHIP/MATERIAL OK PARTITIONS NON-BEARING
Underslab Electrical Inspection - Commercial Partial 05/23/2003
Correction
Resolved
05/23/2003
CONDUIT & BOX INSTALLATION OK TO COVER WHEN READY TO RECEPT DESK RM 103 + TO CONF TABLE RM 106
Correction
Partial Correction
05/23/2003
CONDUIT & BOX INSTALLATION ONE @ CONF AREA 130 APPROVED; OK TO COVER
Underslab Plumbing Inspection - Commercial Passed 05/28/2003
Correction
Resolved
05/28/2003
UNDER-FLOOR DWV PIPING SLOPED TO DRAIN. OK TO COVER WHEN READY. PHASE 1 (W 1/2) OF AREA A EXCAVATED; LAID; JOINED
Correction
Resolved
05/28/2003
UNDER-FLOOR DWV PIPING EXCAVATED; LAID; JOINED; SLOPED TO DRAIN. OK TO COVER WHEN READY. AREA "A" UPPER SUBSTANTIALLY PER M1.1A
All Rough Inspection - Commercial Partial 06/19/2003
Correction
Resolved
06/19/2003
IN-WALL SYSTEMS ROUGH LOWER LEVEL ONLY ELECT WORK ONLY APPROVED
Correction
Resolved
06/19/2003
CEILING DROP @ RECEP 103; L,G. STEEL STUD PARTITIONS WORKMANSHIP/MATERIAL OK PARTITIONS NON-BEARING
Correction
Partial Correction
06/19/2003
IN-WALL SYSTEMS ROUGH - PARTIAL AT WOMENS 138 N WALL ONLY; MENS 137. H&C WATER + DWV PIPING FOR S-1 @ HALL 122 NW CORNER. H&C WATER + DWV PIPING + FIXTURE CARRIERS
All Rough Inspection - Commercial Partial 06/23/2003
Correction
Resolved
06/23/2003
IN-WALL SYSTEMS ROUGH - PARTIAL AT WOMENS 138 N WALL ONLY; MENS 137. H&C WATER + DWV PIPING FOR S-1 @ HALL 122 NW CORNER. H&C WATER + DWV PIPING + FIXTURE CARRIERS
Correction
Partial Correction
06/23/2003
IN-WALL SYSTEMS ROUGH - PARTIAL H&C WATER & DWV PIPING + FIXTURE CARRIERS AT WOMENS 138 SW CORNER NOW COMPLETE & APPROVED AREA "A" UPPER LEVEL IN-WALL COMPLETE
Miscellaneous Inspection Not Ready 06/26/2003
Correction
Resolved
06/26/2003
DRAWING SHEET A2.1
Correction
Corrective Action Required
06/26/2003
READINESS FOR INSPECTION G.C. TRAILER LOCKED; NO ACCESS TO PERMIT DRAWINGS. NOT READY FOR INSPECTION NO SPECIFICS ON REQUEST NO P.C. OR G.C. FOUND
All Rough Inspection - Commercial Passed 07/28/2003
Correction
Resolved
07/28/2003
IN-WALL SYSTEMS ROUGH - PARTIAL
Above Ceiling Inspection Failed 07/28/2003
Correction
Corrective Action Required
07/28/2003
ELECTRICAL WORK LIGHT FIXTURES NOT SET TERMINATIONS >CLOSE BOXES
Correction
Partial Correction
07/28/2003
HVAC WORK INCOMPLETE DIFFUSERS/CONNECTIONS
Correction
Corrective Action Required
07/28/2003
TEMPORARY ELECTRICAL WIRING NOT REMOVED
Correction
Corrective Action Required
07/28/2003
WALLS DESIGNATED AS FIRE-RATED BOTH SIDES OF WALL CHECK DRAWINGS TO VERIFY ANY ARE SEALED
Miscellaneous Inspection Passed 07/28/2003
Correction
Resolved
07/28/2003
READINESS FOR INSPECTION
Rough Plumbing Inspection - Commercial Passed 07/28/2003
Correction
Resolved
07/28/2003
None
Underslab Electrical Inspection - Commercial Passed 07/28/2003
Correction
Resolved
07/28/2003
CONDUIT & BOX INSTALLATION ONE @ CONF AREA 130
Above Ceiling Inspection Not Ready 08/01/2003
Correction
Corrective Action Required
08/01/2003
READINESS FOR INSPECTION PAT SUTLIF OF ACI FRANKHEISER HUTCHINS ARCHITECTS THAT FIRE-RATING OF CORRIDOR WALLS AND ABOVE-CEILING HVAC RA PLENUM SPACES IS UNDER CONSIDERATION BY A/E, GC, AND PROJECT OWNER. SEE RELATED CITATIONS ON PREVIOUS INSPECTION. LS CODE ADMINISTRATION WAS INFORMED 8/1/03 BY
Above Ceiling Inspection Partial 08/04/2003
Correction
Resolved
08/04/2003
ELECTRICAL WORK
Correction
Resolved
08/04/2003
HVAC WORK
Correction
Resolved
08/04/2003
TEMPORARY ELECTRICAL WIRING
Correction
Corrective Action Required
08/04/2003
WALLS DESIGNATED AS FIRE-RATED EXCEPT FOR WORK & INSPECTION ACCESS @ CORRIDOR WALLS VERIFY ALLARE FIREBLOCKED OKTO INSTALL CEILING TILE
Correction
Resolved
08/04/2003
READINESS FOR INSPECTION
Above Ceiling Inspection Passed 08/11/2003
Correction
Resolved
08/11/2003
WALLS DESIGNATED AS FIRE-RATED TO THE EXTENT FEASIBLE, PER ACI / FRANGKISER HUTCHENS REPORT OF ON-SITE MEETING HELD 8/4/03. OK TO COMPLETE INSTALLATION OF CEILING TILE. CORRIDOR WALLS ARE NOW FIRE/SMOKE BLOCKED
Occupancy Inspection - Codes Commercial Partial 08/13/2003
Correction
Partial Correction
08/13/2003
OCCUPANCY STATUS DO NOT ALLOW OCCUPANCY BY STUDENTS UNTIL REINSPECTION & AUTHORIZATION ARE OBTAINED OK FOR TEACHERS & ADMIN THROUGH 8/15/03
Occupancy Inspection - Codes Commercial Partial 08/19/2003
Correction
Partial Correction
08/19/2003
OCCUPANCY STATUS OF PARKING LOT CONSTRUCTION COMPLETION OK THROUGH 8/29/03 PENDING P & D APPROVAL
Occupancy Inspection - Codes Commercial Passed 12/12/2003
Correction
Resolved
12/12/2003
OCCUPANCY STATUS ISSUE COFO CLOSE PERMIT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home