Internal Plan Review (Res)
|
Approved
|
08/26/2003
|
10/29/2010
|
|
|
|
Correction
CA - This is an "at risk permit". Construction shall be in accordance with plans submitted for permit approval. The applicant understands that issuance of this permit does not guaranty issuance of a full permit.
|
|
Correction
A note should be provided indicating a Reduce Pressure Zone (RPZ) principal backflow prevention device will be placed inside the building on the domestic water service line prior to the carbonated beverage dispenser(s) and ice maker(s).
|
|
Correction
CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
|
|
Correction
CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
|
|
Correction
Fire Department; IFC 1003.3.1.8 Egress doors shall be readily openable from the egress side without the use of akey or special knowledge or effort. Exit doors shall not be locked, chained, barred, latched or otherwise rendered unusable. All locking devises shall be of an approved type. IFC 1003.3.1.8
|
|
Correction
CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
|
|
Correction
CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
|
|
Correction
CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
|
|
Correction
Calculations must be provided for determining the size and volume of the solids interceptor.
|
|
Correction
All backflow prevention assemblies must be tested and reports filed with the Lee's Summit Water Utilities Backflow Division (816-969-7636) within 30 days from the date installed.
|
|
Correction
A grease/solids interceptor must be shown with an indication of size, type and detail of the interceptor.
|
|
Correction
Backflow prevention assembly must be located in an accessible location, min. 12" from floor, min. 6" from wall, max. 48" from floor.
|
|
|