Summary
B0202153
Building Permit - Commercial
Final Completion
CITY OF LEES SUMMIT
ALTERATION COMMERCIAL
ARNOLD HALL ALTERATION
12/09/2002
01/31/2003
07/30/2003
11/25/2003
Locations
Contacts
HOLLIS & MILLER GROUP, INC, Address:220 NW EXECUTIVE WAY  
LEES SUMMIT SENIOR CENTER, Address:123 SE 3RD ST  
CITY OF LEES SUMMIT, Address:PO BOX 1600  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 06/07/2003 10/29/2010
Correction

CA - ANSI A117.1-1998 404.2.7 - Door Hardware. Handles, pulls, latches, locks, and other operable parts on accessible doors shall have a shape that is easy to grasp with one hand and does not require tight grasping, pinching, or twisting of the wrist to operate. Such hardware shall be 34 inches minimum and 48 inches maximum above the floor or ground. Where sliding doors are in the fully open position, operating hardware shall be exposed and usable from both sides.
Correction

CA - For the Health Department inspection contact Bob Thomas with the Jackson County Public Works Department at 816-881-4530. Occupancy approval is required by the City of Lee's Summit prior to issuance of any type of occupancy.
Correction

Fire Department; Extension cords and flexible cords shall not be a substitute for permanent wiring. Extension cords and flexible cords shall not be affixed to structures, extended through walls, ceilings or floors, or under doors or floor cove-ings, nor shall such cords be subject to environmental damage or physical impact.
Correction

A grease/solids interceptor must be shown with an indication of size, type and detail of the interceptor.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

CA - LSCO 7-162 - It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code. Inspection requests shall be made in advance and in accordance with the most current written policies of the Codes Administration Department.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

Fire Department; Portable fire extinguishers shall be installed in occupancies and locations as set forth in the IFC Sec. 906 and as required by the Code Offical. Fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Correction

Fire Department: Fire protection systems shall be maintained in accordance with the original installation standards for that system. Required fire protection systems shall be extended, altered, or augmented as necessary to maintain and continue pro-tection whenever the building is altered, remodeled or added to.
Correction

Fire Department. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. The plans and specifications shall bear a State of Missouri licensed engineers seal. This includes fire sprinkler systems, grease hood and duct suppression systems as well as other fire suppression system.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Correction

CA - Each structure shall have the address of that structure visibly posted on the jobsite throughtout the construction process.
Correction

CA - No merchandise, stock, interior furnishings or supplies shall be placed in this facility without approval from the City of Lee's Summit.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - Information on the hood system was not provided at the time of permit application.
Correction

Fire Department-IFC 609.2 Where required. A Type I hood shall be installed at or above all commercial food heat-processing appliances that produce grease vapors or smoke. Exceptions: Food heat-processing appliances installed within a dwelling unit. 609.2.1 Type I hood. A Type I hood shall be installed at or above all commercial food heat-processing appliances that produce grease vapors or smoke. 609.2.2 Domestic cooking appliances used for commercial purposes. Domestic cooking appliances utilized for commercial purposes shall be provided with Type I hoods as required for the type of appliances and processes in accordance with Sections 609.2 and 609.2.1.
Fees
Paid Fees Amount Paid Owing Date Paid
25 Mechanical Permit Fees $21.50 $21.50 Paid 01/31/2003
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Partial 09/30/2003
Correction
Resolved
09/30/2003
INSTALLATION OF WALLBOARD PRESERVED FOR REINSPECTION OF DWV STACKS WHEN ABOVE-CEILING INSPECTION IS REQUESTED. OK TO PROCEED WHEN READY IF INSPECTION ACCESS IS
Correction
Corrective Action Required
09/30/2003
IN-WALL SYSTEMS ROUGH SUPPORT STACKS TO STRUCTURE PLUMBING DWV STACKS NOT SUPPORTED
Above Ceiling Inspection Passed 10/30/2003
Correction
Resolved
10/30/2003
None ABOVE CEILING APPROVE D KITCHEN AREA
Occupancy Inspection - Codes Commercial Failed 10/30/2003
Correction
Corrective Action Required
10/30/2003
NOT READY
All Rough Inspection - Commercial Passed 11/06/2003
Correction
Resolved
11/06/2003
IN-WALL SYSTEMS ROUGH PLUMBING DWV STACKS APPROVED ON ABOVE-CLG
Occupancy Inspection - Codes Commercial Failed 11/06/2003
Correction
Resolved
11/06/2003
NOT READY
Correction
Corrective Action Required
11/06/2003
Receive Water Utilities Approval
Correction
Corrective Action Required
11/06/2003
Receive Fire Department approval
Occupancy Inspection - Codes Commercial Passed 11/24/2003
Correction
Resolved
11/24/2003
Receive Water Utilities Approval NO ISSUES NOTED THIS DATE
Correction
Resolved
11/24/2003
Receive Fire Department approval
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home