Summary
B0200961
Building Permit - Commercial
Final Completion
RAYTOWN TEACHERS CREDIT UNION
ALTERATION COMMERCIAL
INSTALL ATM MACHINE
06/11/2002
06/11/2002
12/08/2002
07/16/2002
Locations
Contacts
HOUSE AND RENNER CONST., INC., Address:5403 W 40 HWY  
RAYTOWN TEACHERS CREDIT UNION, Address:10021 E 66TH TER  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 12/08/2002 10/29/2010
Correction

CA - This permit was reviewed and issued over the counter. Additional requirements may be determined in the field by the inspectors.
Correction

CA - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
Correction

CA - The occupancy and or final inspection shall be scheduled with the Codes Administration Department and requires a minimum of two (2) working days notice. Codes Administration will contact the appropriate city departments and will notify the applicant of the date and time the inspection will be performed.
Correction

CA - Any deviation from the approved plans shall be approved by the City of Lee's Summit. This shall include but is not limited to building layout, facilities provided, building materials and equipment, finishes used, landscaping and site improvements. Information about the changes shall be submitted to the Codes Administration Department for review and a determination will be provided within five (5) working days.
Correction

CA - LSCO Chapter7, Section 117 - Materials, equipment, and devices approved by the building official shall be constructed and installed in accordance with such approval.
Correction

CA - LSCO 7-134 - Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. Permits for exterior work, i.e., walls, fences, decks, patios, patio covers and similar type work requiring permits, as well as permits for residential room additions and remodels shall be limited to 180 days duration. Permits for other new construction shall be limited to one-year duration. The building official official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each.
Correction

CA - LSCO7-168 - The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
Correction

P & D - Sign permits must be obtained for all signs prior to installation. All signs shall comply with the sign requirements outlined in the UDO, Article 13.
Fees
Paid Fees Amount Paid Owing Date Paid
24 BLDG Permit Fees $20.00 $20.00 Paid 06/11/2002
24 BLDG Plan Check Fees $3.50 $3.50 Paid 06/11/2002
25 Electrical Permit Fee $15.00 $15.00 Paid 06/11/2002
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Rough Framing Inspection - Commercial Passed 06/17/2002
Rough Electrical Inspection - Commercial Passed 06/17/2002
Correction
Resolved
06/17/2002
None IN WALL SYSTEMS APPROVED OK TO SHEETROCK COVER 1900 BOX ABOVE CEILING
Occupancy Inspection - Codes Commercial Passed 07/15/2002
Correction
Resolved
07/15/2002
None ATM MACHINE AND REQD INSPECTIONS COMPLIANT
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home