Review Type |
Outcome |
Est. Completion Date |
Completed |
Internal Plan Review (Res)
|
Approved
|
09/02/2000
|
10/29/2010
|
|
|
|
Correction
Codes Administration- Erosion control shall be provided in conformance with Article VIII, Section VIII(c) & (d) and details 48 and 48A of the City of Lee's Summit Design and Construction Manual. Erosion control devices shall be installed and maintained during all phases of the construction process. Failure to provide or maintain erosion control may result in an issuance of a stop work order which is authorized by Article I, Section XXIV.
|
|
Correction
Codes Administration- The ground immediately adjacent to the foundation shall be sloped away from the building not less than 1 inch per 12 inches for a minimum distance of 6 feet measured perpendicular to the face of the wall or an approved alternate method of diverting water away from the foundation shall be used. Consideration shall be given to possible additional settlement of the backfill when establishing final ground level adjacent to the foundation. (UBC Appendix Section 2920(b).
|
|
Correction
Codes Administration- The openings of foundation drains which discharge to daylight shall be exposed to daylight and shall not be covered during grading, or installation of sod. Sump pumps or exterior drains which control stormwater shall not be connected to the sanitary sewer.
|
|
Correction
Codes Administration - Retaining walls over 4 feet in height measured from the bottom of the footing to the top of the wall shall be designed and sealed by a professional engineer or architect registered in the State of Missouri.
|
|
Correction
Codes Administration - A Temporary Certificate of Occupancy will only be granted when all life safety issues have been completed.
|
|
Correction
Codes Administration - Requests for footing inspections shall be made when the footings are complete. All forms shall be in place and all reinforcement completed prior to the inspection request.
|
|
Correction
Codes Administration - Every permit issued by the building official under the provisions of this code shall expire by limitation and become null and void if the building or work authorized by such permit is not commenced within 180 days from the date of such permit, or if the building or work authorized by such permit is suspended or abandoned at any time after the work is commenced for a period of of 180 days. (1991 Uniform Building Code, Section 303(d).)
|
|
Correction
Codes Administration - The disposal of demolition waste is regulated by the Department of Natural Resources under Chapter 260 RSMO. Such waste, in types and quantities established by the department, shall be taken to a demolition landfill or a sanitary landfill for disposal.
|
|
Correction
Codes Administration - It shall be unlawful for any person to engage in any business or manufacturing within the City without first having obtained a license therefor, paying the license fee, and registering the business or manufacturer with the Director of Finance or the Director's representative. (Lee's Summit Code of Ordinances, Section 28-24.) It is the general contractors responsiblity to make sure that all the trades on their project are licensed with the City of Lee's Summit.
|
|
Correction
Codes Administration- Foundations supporting wood shall extend at least 6 inches above the adjacent finished grade. (UBC Section 2907)
|
|
Correction
Codes Administration- Foundation plates or sills shall be bolted to the foundation wall with not less than 1/2 inch nominal diameter steel bolts embedded at least seven inches into the concrete or masonry and spaced not more than six feet apart. There shall be a minimum of two bolts per piece with one bolt not more than twelve inches of the end of each piece. A properly sized nut and washer shall be tightened on each bolt to the plate. (UBC Section 2907.(f))
|
|
Correction
Codes Administration- It shall be the duty of the person doing the work authorized by a permit to notifiy the Building Inspections Division that such work is ready for inspection. (UBC Section 305.(c))
|
|
Correction
Codes Administration- Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the Building Official. The Building Official, upon notification, shall make the requested inspections and shall either indicate that portion of the construction is satisfactory as completed, or shall notify the permit holder or an agent of the permit holder wherein the same fails to comply with this code. Any portions which do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the Building Official. (1991 Uniform Building Code, Section 305.(d).)
|
|
Correction
Codes Administration- A reinspection fee may be assessed for each inspection or reinspection when such portion of work for which inspection is called is not complete or when corrections called for are not made. ( UBC Section 305.(g))
|
|
|